5th Street reconnection (Samatar Crossing)

The City of Minneapolis proposes to reconnect 5th Street South between 11th Avenue South and 15th Avenue South as a local multimodal connection that will include an off-street bicycle facility and an

Project status

Completed.

Project details

The City of Minneapolis proposes to reconnect 5th Street South between 11th Avenue South and 15th Avenue South as a local multimodal connection that will include an off-street bicycle facility, and an enhanced pedestrian walkway. 

Project type

Construction and Reconstruction

Project limits

Connecting 11th Avenue South to 15th Avenue South

Construction schedule

Phase 1 - 2017 (August to December 2017) -- East side of the 5th Street Bridge, no impact to Vehicular traffic- Completed
Phase 2 -2018 - West of the 5th Street Bridge, minor impact to traffic, Bridge remains closed; Detour signs for Bikes/Peds are in place

Phase 2 Construction is anticipated to be completed mid-summer 2018.

Public meetings:

Preconstruction Open House

Friday, August 18, 2017, at 5 p.m.
Brian Coyle Center
420 15th Avenue South
Minneapolis, MN 55454

Preconstruction Open House Flyer

Project information:

Project Layout

Project Rendering

Project updates

Future updates will be posted here.

 

Contact us

Public Works

Phone

612-673-2352

Online

Contact the Director of Public Works

Address

City Hall
350 Fifth St. S.
Room 203
Minneapolis, MN 55415

Request accessible format

If you need help with this information, please email 311, or call 311 or 612-673-3000.

Please tell us what format you need. It will help us if you say what assistive technology you use.