Broadway St NE reconstruction

The Broadway St NE roadway will be stripped from a four-lane roadway to a two-lane roadway with center turn lanes.
Project location

Project Status

Completed.

Project details

Project description:
This project will reconstruct approximately 0.8 miles of Broadway Street NE from Stinson Boulevard to Industrial Boulevard. The roadway will be striped from a four lane roadway to a two lane roadway with center turn lanes. A major component of this project is the construction of currently missing multi-modal elements, including adding 0.7 miles of sidewalk and construction of a new off-street bicycle facility along the project area. A sidewalk will be added to the north side of the street and the off-street, multi-use trail will be constructed on the south side of the street. Existing sidewalks gaps make it difficult for pedestrians to walk to and from transit stops to access employers and businesses within the area. The proposed sidewalk additions will improve walkability for pedestrians and provide greater access to transit stops, retail shopping destinations and a key job concentration center.

Project location:
Broadway Street NE from Stinson Boulevard to the City Limits (Industrial Boulevard)

Project start date:
Construction activities started on April 30, 2018; and the estimated completion date of the project is November 30, 2018.

Project documents:
Broadway Street Northeast Council-Approved Layout

Neighborhood Meeting Presentation on April 16, 2018

 

street view

     

intersection at stinson blvd
 

Request accessible format

If you need help with this information, please email 311, or call 311 or 612-673-3000.

Please tell us what format you need. It will help us if you say what assistive technology you use.

Contact us

 

Public Works

 
 

Phone

612-673-2352

 
 

Address

City Hall
350 Fifth St. S.
Room 203
Minneapolis, MN 55415