28th Ave S reconstruction

Between 2018 and 2019, the City of Minneapolis reconstructed 28th Ave S in South Minneapolis between 58th St E and the city limits (south of 59th 1/2 St E).
 

 

Project location

Project status

Completed.

About

The project will include a new road surface, sub-base, curbs, sidewalk, boulevard space and utilities as needed. The street is in poor condition in this entire length, particularly the section with the concrete pavement. Pavement cores have revealed that the concrete base under the asphalt pavement on the south end of the project has also failed and requires replacement.  This project will replace all of the sidewalk and add boulevard green space where feasible.

Project details

Project limits

58th St E to City Limits (south of 59 ½ St E)

Construction start date

2018

Duration of construction

It is anticipated that the roadway portion of the project will be completed and open fully to vehicle traffic by the end of the 2018 construction season.  It is also anticipated that the existing sidewalk will remain in place to provide a hard surface over the winter of 2018-19.  It will be replaced in 2019 and sod and trees will be installed in 2019.

Traffic impact

There is a residential neighborhood located south of State Hwy 62, and 28th Ave S will be required to maintain sufficient access to this neighborhood. It is expected that 28th Ave S will be at one lane during construction activities, and this may cause delays. It is expected that the ramps to and from State Hwy 62 will be closed, and 34th Ave S will be the detour for these ramps. During certain activities, such as the final layer of asphalt paving, 28th Ave S may need to be closed and access will be maintained to emergency vehicles only. Residents will be notified in advance when this occurs.

Project layout

Project Layout

Project updates

March 26, 2019 update: Sidewalk replacement will start during the week of April 8th. Later this spring/early summer, Minneapolis Park and Recreation will plant trees in the boulevard. In mid- to late summer, the asphalt pavement will be sealcoated and final striping will take place.

February 22, 2019 update: The street is substantially complete and open to traffic.  In 2019, sidewalk replacement and tree planting will be completed.  The street will be sealcoated and receive final striping in the summer of 2019.

 

Contact us

 

Public Works

 
 

Phone

612-673-2352

 
 

Address

City Hall
350 Fifth St. S.
Room 203
Minneapolis, MN 55415