Phased permit

A large commercial construction project may be eligible for a phased permit.

How it works

A phased permit lets you start part of your work before you submit documents for the entire project.

Eligibility

Your project must be a new building that: 

  • Costs more than $25 million to build; or
  • Takes more than 22 months to build

Single-family homes, duplexes and townhouses are not eligible.

See MN State Building Code, section 1300.0130, subp 8