34th Avenue South Street Reconstruction

The City of Minneapolis is reconstructing 34th Avenue South between East Minnehaha Parkway and 58th Street East. The project is scheduled to occur over the course of the 2019 and 2020 construction seasons and will consist of improvements to the roadway, sidewalk and utilities.

34th Ave S from 51st St to 58th St will be completed in 2019; 51st St to Minnehaha Pkwy is planned for 2020.

34th St Ave S 

Project Status

 CIP Status Stage 4: Construction

Project Details

Project Type

This project encompasses the entire right-of-way and include full removal of the existing street, subgrade correction, new pavement, curb and gutter, driveways, sidewalk as needed, streetscape elements as needed, utility work as needed, pavement markings, signals, and signage.

Project Limits

The 34th Ave South project is located in south Minneapolis from East Minnehaha Parkway to 58th Street East.

Construction Timeline

34th Ave S Timeline Graphic Revised

Photos

34th Ave S project photo 11-8-19_2

34th Ave S project photo 11-8-19_1

34th Ave S after street reconstruction

Project Meetings

Community Meeting #1

Nokomis East Neighborhood

November 28, 2016 – 6:00 p.m.
4313 54th Street East
Minneapolis, MN 55417
Meeting Presentation
Project Fact Sheet 

Community Meeting #2

Nokomis East Neighborhood
January 25, 2017 – 6:00 p.m.
Lake Nokomis Lutheran Church
5011 31st Avenue South
Minneapolis, MN 55417
Meeting Presentation 

Community Meeting #3

Nokomis East Neighborhood
January 30, 2018 – 6:30 p.m.
Lake Nokomis Lutheran Church
5011 31st Ave South
Minneapolis, MN 55417
Meeting Presentation 

Community Meeting #4

Preconstruction Meeting

The Department of Public Works will hold an informational meeting to address questions about 34th Ave S reconstruction project. The meeting will be held on Tuesday, April 2, 2019. Below is the detail.

Tuesday, April 2, 2019
6:30 p.m.
Morris Park Recreation Center
5531 39th Ave S
Minneapolis MN 55417           

Business Meeting

Nokomis East Business Association and Nokomis East Neighborhood Association
McDonald's Liquors and Wine
Lower Level Event Room
5010 S. 34th Avenue South
Minneapolis, MN 55417 

March 13, 2017 – 4:00 p.m.

Project Updates

July 10, 2020 Update

Work completed this week

  • Max Steininger has been working on sub grade correction.
  • Max Steininger sub-contractor Kusske construction has been working on underground utility work. 

Anticipated work for next week

  • Finishing subgrade preparation/correction
  • 50th St E intersection pavement removal

Street closure

  • 50st St E intersection closure starting date has been postponed to July 16th. Please understand that this schedule is subject to change due to weather, unforeseen circumstances and current situation like COVID-19.

July 2, 2020 Update

There will be no work or stakeholder meeting on Friday, July 3, 2020.

Phase III-b (50th St E – Minnehaha Parkway)

  • Max Steininger sub-contractor Kusske construction has been working on underground utility work.
  •  CenterPoint Energy's contractor Michaels has been working on removing abandoned gas pipe.

Anticipated Work for next week:

  • Finishing underground utility
  • Finishing removing abandoned gas pipe
  • Start subgrade preparation.

Street Closure

  • 50 St E intersection is tentatively scheduled to be closed from July 8th to July 18th. This closure is necessary in order to complete some of major construction activities at the intersection, such as remove concrete pavement and sidewalk, underground utilities work and subgrade preparation. Please understand that the construction schedules are subject to change due to weather and unforeseen circumstances

June 26, 2020 Update

Phase III-b (34th Ave S from 50th St E to Minnehaha Parkway) 

  • Traffic control and detours are in place.

  • 34th Ave S from 50st St E to Minnehaha will be open only to local traffic but closed to thru traffic
  • Max Steininger completed removal of pavement, curb and gutter
  • Max Steininger sub-contractor Kusske construction has begun working on underground utility work
  • CenterPoint Energy's contractor Michaels has begun removing abandoned gas pipe within phase III-b limit

Anticipated work for next week:

  • Continuing underground utility
  • Continuing removing abandoned gas pipe
  • Relocate fire hydrants
  • Start subgrade preparation

Street Closure:

  • 50st St E intersection is tentatively scheduled to be closed from July 8th to July 18th
  • Advance warning will be in place next week

There will be no work or stakeholder meeting on Friday, July 3, 2020. 

June 26, 2020 Update

Phase III-b (50th St E – Minnehaha Parkway)

  • Traffic control and detours are in place.
  • 34th Ave S from 50st St E to Minnehaha will be open only to local traffic but closed to thru traffic
  • Max Steininger completed removal of pavement, curb and gutter 
  • Max Steininger sub-contractor Kusske construction has begun working on underground utility work. 

CenterPoint work

  • CenterPoint Energy's contractor Michaels has begun removing abandoned gas pipe within phase III-b limit.

Anticipated Work for next week

  • Continuing underground utility 
  • Continuing removing abandoned gas pipe
  • Relocate fire hydrants
  • Start subgrade preparation.

July 3rd

  • There will be no work or stakeholder meeting on Friday, July 3, 2020.

Street Closure

  • 50st St E intersection is tentatively scheduled to be closed from July 8 to July 18.
  • Advance warning will be in place next week. 

June 26, 2020 Update

Phase III-b (34th Ave S from 50th St E to Minnehaha Parkway) 

  • Traffic control and detours are in place.

  • 34th Ave S from 50st St E to Minnehaha will be open only to local traffic but closed to thru traffic
  • Max Steininger completed removal of pavement, curb and gutter
  • Max Steininger sub-contractor Kusske construction has begun working on underground utility work
  • CenterPoint Energy's contractor Michaels has begun removing abandoned gas pipe within phase III-b limit

Anticipated work for next week:

  • Continuing underground utility
  • Continuing removing abandoned gas pipe
  • Relocate fire hydrants
  • Start subgrade preparation

Street Closure:

  • 50st St E intersection is tentatively scheduled to be closed from July 8th to July 18th
  • Advance warning will be in place next week

There will be no work or stakeholder meeting on Friday, July 3, 2020. 

June 19, 2020 Update

Phase III-b (34th Ave S from 50th St E to Minnehaha Parkway) is scheduled to start construction on June 22nd.

  • Advance road closure warnings have been in place. 
  • On Monday, June 22, 2020
    • Traffic control and detours will go in place.
    • 34th Ave from 50th St E to Minnehaha Parkway will be open only to local traffic but closed to thru traffic.
    • 34th Ave S (Max Stinger, the Contractor for 34th Ave S) will mobilize and start by breaking and removing the existing pavement, curb and gutter.  
  • Underground utility work will follow removal of pavement, Curb and Gutter.
  • Center point Energy’s contractor Michaels will remove abandoned gas pipe along 34th Ave S
  • Once the removal and underground utility work completed, grading and concrete work will be followed by placing new asphalt pavement. If the approach to your driveway is in the Phase III-b construction limits, we will notify you in advance of placing your new driveway approach. 
  • Typical working hours will be between 7am and 6pm Monday thru Friday.
  • If there is any weekend or late hour work, we will do our best to post on the project web site and send email update to email subscriber. (if you have any question or need help on email subscription, please call me at 612 900 5848 or email [email protected]
  • Phase III-b is estimated to be substantially completed with new pavement by October. Please understand that the construction schedules are subject to change due to weather, unforeseen circumstances and current situation COVID-19.
  • We will have biweekly remote stake holder meeting. The invitation will be posted on the project web site.

June 10, 2020 Meeting Announcement

The Department of Public Works is holding a virtual kick-off meeting to address any questions that you may have about the 34th Ave S reconstruction project between 50th St E and Minnehaha Pkwy. The meeting will be held on June 12, 2020.

Phase III Pre-Construction Meeting
Friday, June 12, 2020
6:30 - 7:30 p.m.
through Microsoft Teams

How to join the live event

Open the live event link, to join the event.

Join the 34th Ave S Reconstruction Phase III Pre-Construction Neighborhood Meeting

How to ask a question

If you're an attendee and want to ask a question, just:

  • Select Q&A  on the right side of the screen.
  • Type your question in the compose box, and then select Send. If you want to ask your question anonymously, select Ask anonymously.

Ask a question in Teams image

Support for using Microsoft Teams

If you have any questions or comments, please contact me at [email protected] or 612-900-5848.

June 10, 2020 Update

The tentative beginning date for Phase III-b reconstruction (34th Ave S from 50th St E to Minnehaha Parkway) is pushed back from June 15, 2020 to June 22, 2020.

To save yourself time and money, if you have experienced any problems with your sewer and/or water connection it is recommended that you contact a licensed plumber as soon as possible to correct the problem before the street is paved. One problem frequently encountered in connection with street paving is the condition and age of the private water and sewer services from the house or business to the City main in the street. Occasionally, because of the age and condition of these services, they may require repair or replacement within a relatively short period of time after the new paving is completed. So, if you are planning to upgrade your water or sewer service, please call me at 612-900-5848 to coordinate with the project’s schedule.

June 5, 2020 Update

Work completed this week

  • Topsoil
    • Phase III-a (51st to 50th St E)
    • Phase I & II punch lists

Anticipated work for next week

  • Sod
    • Phase III-a (51st to 50th St E)
    • Phase I & II punch lists

Phase III-b (50th St E – Minnehaha Parkway)

34th Ave S from 50th St E to Minnehaha Parkway reconstruction is tentatively scheduled to start on June 15, 2020.

Sewer work

To save yourself time and money, if you have experienced any problems with your sewer and/or water connection it is recommended that you contact a licensed plumber as soon as possible to correct the problem before the street is paved. One problem frequently encountered in connection with street paving is the condition and age of the private water and sewer services from the house or business to the City main in the street. Occasionally, because of the age and condition of these services, they may require repair or replacement within a relatively short period of time after the new paving is completed. So, if you are planning to upgrade your water or sewer service, please call me at 612-900-5848 to coordinate with the project’s schedule.

June 4, 2020 Announcement - Meeting Postponed

This week's biweekly stakeholder meeting has been postponed until next Friday.

Remote Stakeholders Meeting
Friday, June 5, 2020 Friday, June 12, 2020
6:30 - 7:30 p.m.
through Skype

If you would like to attend, or if you have any questions or comments, please contact Menbere Wodajo at [email protected] or 612-673-3716.

May 29, 2020 Meeting Announcement

The Department of Public Works is holding biweekly remote stakeholders meeting to address any questions that you may have about 34th Ave S reconstruction project between 51st St E and Minnehaha Pkwy. The next meeting will be held on June 5, 2020.

Remote Stakeholders Meeting
Friday, June 5, 2020
6:30 - 7:30 p.m.
through Skype

How to join the meeting

To join the meeting, please click the link below.

Join the 34th Ave S Reconstruction Biweekly Stakeholders Meeting (June 5, 2020)

If you have any questions or comments, please contact me at [email protected] or 612-900-5848.

May 29, 2020 Update

Work completed this week

  • 51st to 50th St E (including 51st intersection)
    • Xcel Pole relocation
    • Final grading
    • Asphalt paving (the first three lifts)

Anticipated work for next week

  • Topsoil
    • Phase III-a (51st to 50th St E)
    • Phase I & II punch lists

Phase III-b (50th St E – Minnehaha Parkway)

34th Ave S from 50th St E to Minnehaha Parkway reconstruction is tentatively scheduled to start on June 15, 2020.

To save yourself time and money, if you have experienced any problems with your sewer and/or water connection it is recommended that you contact a licensed plumber as soon as possible to correct the problem before the street is paved. One problem frequently encountered in connection with street paving is the condition and age of the private water and sewer services from the house or business to the City main in the street. Occasionally, because of the age and condition of these services, they may require repair or replacement within a relatively short period of time after the new paving is completed. So, if you are planning to upgrade your water or sewer service, please call me at 612-900-5848 to coordinate with the project’s schedule.

May 22, 2020 Update

Work completed this week

  • North of 51st – south of 50th St E
    • Placing east sidewalk
    • Streetlight foundations
    • Bus pad
  • 51st St E intersection
    • Curb & Gutter
    • Sidewalk (SW & SE corner)
  • Phase I & II Punch lists 
    • Sidewalk replacement

Anticipated work for next week

  • Phase III-a (51st to 50th St E)
    • Asphalt paving
    • Topsoil
  • Phase I & II Punch lists
    • Topsoil

May 15, 2020 Meeting Reminder

The Department of Public Works is holding biweekly remote stakeholders meeting to address any questions that you may have about 34th Ave S reconstruction project between 51st St E and Minnehaha Parkway. The next meeting will be held on May 22, 2020.

Remote Stakeholders Meeting
Friday, May 22, 2020
1:00 - 2:00 p.m.
through Skype

How to join the meeting

To join the meeting, please click the link below.

Join the 34th Ave S Reconstruction Biweekly Stakeholders Meeting (May 22, 2020)

For those people who received email invitation on April 21, you can join by clicking the link above but still you can join by clicking the link in the email or your calendar. If you have any questions or comments, please contact me at [email protected] or 612-900-5848.

May 15, 2020 Update

Work completed this week

  • North of 51st – south of 50th St E
    • Placing curb & gutter
    • Placing west sidewalk
    • Driveways
  • 51st St E intersection
    • Placing curb & gutter
    • Placing sidewalk (NW & NE corner)
    • Driveway

Anticipated work for next week

  • Between north of 51st and south of 50th St E
    • Grading & pouring east side sidewalk 
    • Bus pad
    • Streetlight foundation
  • 51st St E intersection
    • Placing curb & gutter
    • Placing sidewalk (SW & SE corner)

May 8, 2020 Update

Work completed this week

  • North of 51st – south of 50th St E
    • Subgrade correction.
    • Light conduit installation (Crossings)
  • 51st St E intersection
    • Storm and Sanitary work
    • Soil correction 
    • Light conduit installation

Anticipated work for next week

  • Between north of 51st and south of 50th St E
    • Placing curb & gutter
    • Removing, grading and pouring sidewalks
    • Placing driveways and bus pad
  • 51st St E intersection
    • Placing curb & gutter
    • Placing driveway

May 6, 2020 Meeting Notice

Meeting Announcement

The Department of Public Works is holding biweekly remote stakeholders meetings to address any questions that you may have about the 34th Ave S project between 51st St E and Minnehaha Pkwy. The next meeting is on May 8, 2020.

Remote Stakeholders Meeting
Friday, May 8, 2020
1:00 - 2:00 p.m.
through Skype

If you would like to attend the meeting, please contact Menbere Wodajo:

[email protected] or 612-900-5848

May 1, 2020 Update

Work completed this week

  • North of 51st – south of 50th St E
    • Max Steininger continue working on subgrade correction and grading.
    • Premier (Max Steininger sub-contractor) is installing light conduit.
  • 51st St E intersection
    • 51st St E intersection is closed to traffic.
    • Michaels, (CenterPoint Energy's contractor) removed abandoned gas pipe
    • Kusske construction (Max Steininger sub-contractor) has begun working on Storm and Sanitary improvement
    • HANCO (Century links’ contractor) is working to mitigate underground utility conflict

Anticipated work for next week

  • Between north of 51st and south of 50th St E
    • Premier (Max Steininger sub-contractor) will continue installing light conduit
    • West side sidewalk will be removed.
  • 51st St E intersection
    • Kusske construction (Max Steininger sub-contractor) will keep working on storm and sanitary improvement. 
    • HANCO (Century links’ contractor) will keep working to mitigate underground utility conflict.
    • Max Steininger will start working on subgrade correction and grading

April 24, 2020 Update

Work completed this week

  • 51st St E closure advance warning is in place.
  • Work completed in the past week (north of 51st St E and south of 50th St E)
    • Pavement Removal
    • Storm and Sanitary work
    • Fire hydrant relocation
    • Abandoned gas pipe Removal
  • Max Steininger has begun working on subgrade preparation.

Anticipated work for next week

  • Between north of 51st and south of 50th St E
    • Max Steiniger will keep working on subgrade preparation
    • Premier (Max Steiniger sub-contractor) will start installing light conduit

Street closures

  • 51st St E intersection closure: 51st St E intersection will be closed to traffic from Monday April 27th to May 7th. This closure is necessary in order to complete some of major construction activities at the intersection, such as remove concrete pavement and sidewalk, underground utilities work and subgrade preparation. Please understand that the construction schedules are subject to change due to weather and unforeseen circumstances
  • Kusske construction (Max Steiniger sub-contractor) will work on storm and sanitary. 
  • Century links will work to mitigate underground utility conflict.
  • Michaels, (CenterPoint Energy's contractor) will remove abandoned gas pipe 

April 17, 2020 Update

Work completed this week

  • Traffic control and detours are in place.
  • 34th Ave S from 51st St E to 50th St E will be open only to local traffic but closed to thru traffic
  • Max Stinger has begun working on phase III-a
    • Removed pavement, curb & gutter and portion of sidewalk.
    • Max Steiniger sub-contractor Kusske construction has begun working on installing underground utility pipe and structures. 
  • CenterPoint:
    • CenterPoint Energy's contractor Michaels has begun removing abandoned gas pipe within phase III-a limit.

Anticipated work for next week

  • Continuing underground utility 
  • Continuing removing abandoned gas pipe
  • Relocate fire hydrants
  • Start subgrade preparation.

Street closures

  • 51st St E intersection is tentatively scheduled to be closed from April 27 to May 7, 2020 
  • Advance warning will be in place next week. 

April 17, 2020 Stakeholders Meeting Notice

Meeting Announcement

The Department of Public Works will be holding a remote stakeholders meeting to address any questions that you may have about the 34th Ave S project between 51st St E and Minnehaha Pkwy.

Remote Stakeholders Meeting
Friday, April 24, 2020
1:00 - 2:00 p.m.
through Skype

If you are interested to attend the meeting, please contact Menbere Wodajo:

[email protected] or 612-900-5848

April 10, 2020 Update

Phase III Updates

  • Advance road closure warnings have been in place. 
  • On Monday, April 13, 2020:
    • Traffic control and detours will go in place.
    • 34th Ave from 51st St E to 50th St E will be open only to local traffic but closed to thru traffic.
    • Keewaydin Pl from 31st Ave S to 34th Ave S will temporarily be a two-way street to assist the traffic flow on this corridor.
    • No parking will be posted on Keewaydin north side except disabled parking spaces.
    • Temporary new stop sign will be in place at 31st Ave S & Keewyadin intersection (for west bound)   
    • 34th Ave S (Max Stinger, the Contractor for 34th Ave S) will mobilize and start by removing the existing pavement, curb and gutter.  
  • Underground utility work will follow removal of pavement, Curb and Gutter.
  • Center point Energy’s contractor Michaels will remove abandoned gas pipe along 34th Ave S
  • In addition, Center Point & Century link will work in conjunction with Contractor to mitigate any conflict with proposed City infrastructure in the corridor.
  • Once the removal and underground utility work completed, grading and concrete work will be followed by placing new asphalt pavement. If the approach to your driveway is in the Phase III-a construction limits, we will notify you in advance of placing your new driveway approach. 
  • Typical working hours will be between 7am and 6pm Monday thru Friday.
  • If there is any weekend or late hour work, we will do our best to post on the project web site and send email update to email subscriber. (if you have any question or need help on email subscription, please call me at 612-900-5848 or email [email protected]
  • Phase III-a is estimated to be substantially completed with new pavement by June. Please understand that the construction schedules are subject to change due to weather, unforeseen circumstances and current situation COVID-19.
  • We will have biweekly remote stake holder meeting. The invitation will be posted here on the project web site.

April 3, 2020 Meeting Notice

Meeting Announcement

The Department of Public Works will be holding a remote kick-off meeting to address any questions that you may have about the 34th Ave S project between 51st St E and Minnehaha Pkwy.

Remote Kick-off Meeting
Wednesday, April 8, 2020
2:00 - 3:00 p.m.
through Skype

If you are interested to attend the meeting, please contact Menbere Wodajo:

[email protected] or 612-900-5848

March 20, 2020 Update

All in-person stakeholder and engagement meetings for Public Works projects are cancelled.

Please visit http://www.minneapolismn.gov/cip/index.htm to learn more about all Public Works projects.

Construction resumes

The 34th Ave S reconstruction project is anticipated to resume in your neighborhood. Construction this year will primarily take place along 34th from 51st St E to Minnehaha Parkway. The 2020 project area is shown in blue on the map below.

There are two phases this year. Phase III-a construction, from 51st St E to south of 50Th St E, is tentatively scheduled to begin with pavement removal on April 13th and estimated to be substantially completed with new pavement by end of May. Phase III-b construction, from 50th St E to Minnehaha Parkway, may start by mid-July after 28th bridge is completed. But there will be additional communication from me regarding Phase III-b schedule. Please understand that the construction schedules are subject to change due to weather, current situation and unforeseen circumstances.

The project will include complete removal and replacement of the pavement surface, curb and gutter, storm drains, driveway approaches, some sidewalk, new trees, sod and signal improvements. Once the removals and underground utility work is complete, the new asphalt pavement can be placed. If the approach to your driveway is in the project construction limits, we will notify you in advance of placing your new driveway approach and ask you to park at another location for eight days after concrete placement to allow time for the concrete to cure. During the majority of construction, local access to homes and businesses will be maintained.

Our construction activities are likely to cause you some inconvenience, but we are hopeful that you will be patient and understanding as the work progresses. For our part, we will do our best to keep these inconveniences at a minimum.  If you have any questions or concerns about this improvement project, please call me (Menbere Wodajo) at 612-900-5848. You can also contact the Chief Field Inspector on the Project, Brad Mikiska at 612-297-4660.

Letters were not delivered in person to residents due to COVID-19 social distancing precautions.

Read the full letter from project engineer Menbere Wodajo.

 34th Ave S Project Phases Map

November 15, 2019 Update

Phase I & II (58th St E to 51st St E)

  • Premier, Max Subcontractor is tentatively scheduled to start street light work on Monday November 18th, 2019.
  • This work is estimated to be completed by the end of December 2019. Please understand that this schedule is subject to change due to weather and unforeseen circumstances.
  • There may be some minor work on punch list items.
  • Trees planting is tentatively scheduled for spring 2020.

Phase III

34th Ave S from 51st St E to Minnehaha Pkwy will start spring 2020.

To save yourself time and money, if you have experienced any problems with your sewer and/or water connection it is recommended that you contact a licensed plumber as soon as possible to correct the problem before the street is paved. One problem frequently encountered in connection with street paving is the condition and age of the private water and sewer services from the house or business to the City main in the street. Occasionally, because of the age and condition of these services, they may require repair or replacement within a relatively short period of time after the new paving is completed. So, if you are planning to upgrade your water or sewer service, please call me at 612-673-3716 to coordinate with the project’s schedule.
 

November 8, 2019 Update

Phase I & II

  • Street lights installation work is tentatively scheduled to start on the week of November 18th, 2019
  • Trees planting is tentatively scheduled for spring 2020.
  • There may be some minor work on punch list items.

Phase III

34th Ave S from 51st St E to Minnehaha Pkwy will start spring 2020.

To save yourself time and money, if you have experienced any problems with your sewer and/or water connection it is recommended that you contact a licensed plumber as soon as possible to correct the problem before the street is paved. One problem frequently encountered in connection with street paving is the condition and age of the private water and sewer services from the house or business to the City main in the street. Occasionally, because of the age and condition of these services, they may require repair or replacement within a relatively short period of time after the new paving is completed. So, if you are planning to upgrade your water or sewer service, please call me at 612-673-3716 to coordinate with the project’s schedule.

Completed Work

34th Ave S project photo 11-8-19_2

34th Ave S project photo 11-8-19_1

November 1, 2019 Update

Phases I & II

  • 34th Ave S from 58th St E to 51st St E is substantially completed and open!
  • There may be some minor work on punch list items.
  • Trees planting and Street light installation work are scheduled for spring 2020.

Phase III

34th Ave S from 51st St E to Minnehaha Pkwy will start in spring 2020.

To save yourself time and money, if you have experienced any problems with your sewer and/or water connection it is recommended that you contact a licensed plumber as soon as possible to correct the problem before the street is paved. One problem frequently encountered in connection with street paving is the condition and age of the private water and sewer services from the house or business to the City main in the street. Occasionally, because of the age and condition of these services, they may require repair or replacement within a relatively short period of time after the new paving is completed. So, if you are planning to upgrade your water or sewer service, please call me at 612-673-3716 to coordinate with the project’s schedule.

Thank you for your patience during Phases I & II reconstruction!

Completed Work

34th Ave S Finished Photo_1

Completed pavement on 34th Ave S

34th Ave S Finished Photo_2

Completed pavement on 34th Ave S

October 25, 2019 Update

Work Completed in the Past Week

The final lift of Asphalt for phase II is completed.

  • Striping is completed (Phase I & II)

Anticipated Work for Next Week

  • Tomorrow October 26, 2019.
    • Minnesota sawing (Max subcontractor) is scheduled to finish sawing and sealing from 58th St E to 54th ST E 58th.
    • They have permission to work from 9:00 a.m. to 6:00 p.m. 
    • No parking is allowed on 34th (58th St E - 54th St E)

October 18, 2019 Update

  • The final lift of Asphalt for phase I is completed.
  • The first three lifts of Asphalt for phase Ii is completed
  • Sod is completed for phase I and II

Anticipated Work for the Next Week

  • Tomorrow October 19, 2019.
    • Valley Paving will pave the last lift of Asphalt between 54th St E and 51st St E
    • They have permission to work from 7:00 a.m. to 7:00 p.m. 

Other remaining work

  • Stripping
  • Saw and seal

October 4, 2019 Update

Work Completed in the Past Week

 Road Construction

  • Max completed subgrade correction between 54th and 51st St E
  • Valley Paving (Max subcontractor) have started paving the first three lifts of asphalt between 54th and 51st.
  • Kusske (Max subcontractor) have been adjusting /raising Manholes between 58th and 54th St E

Anticipated Work for the Next Week

Today (October 4, 2019)

  • Valley Paving and Kusske, Max subcontractors have got permission to work up to 8:00 p.m. 

Tomorrow (October 5, 2019)

  • Valley Paving, Max subcontractor is tentatively scheduled to continue paving between 54th and 51st St E.
  • They have permission to work 7:00 a.m. to 6:00 p.m. (No loud noise or equipment 7:00 a.m. to 9:00 a.m.)
  • Kusske, Max subcontractor might work on adjusting /raising manholes at 58th intersection. 

Monday (October 7, 2019)

  • Valley Paving, Max subcontractor is tentatively scheduled to pave the final lift of wear course between 58th and 51st St E and 54
  • They have permission to work 7:00 a.m. to 8:00 p.m.

Other remaining work

  • Placing boulevard top soil/ tree top soil for Phase II-a (54th to 51St E)
  • Installing sign foundations 
  • Placing sod
  • Adjusting/raising Manholes between 54th to 51th St E

September 27, 2019 Update

Work Completed in the Past Week

Completed work

  • 52nd intersection 
    •  Grading for Curb & Gutter.
    •  Place Curb & Gutter
    •  Place sidewalk
  • Bus pad and driveway placement between 54th and 51st E
  • Bus pad repair mid-block of 58th and 56th St E
  • Placing Curb & Gutter between 54th and 51st E
  • Sidewalk for bus shelter at NW corner of 58th St E
  • Max has been working on subgrade correction at 52nd intersection and between 52nd and 51st.
  • Premier has been installing lighting conduit between 54th and 52nd St E. 

Anticipated Work for the Next Week

Weekend Work (October 5th, 2019)

  • Valley Paving, Max subcontractor is tentatively scheduled to pave the final lift of Asphalt for Phase I (58th St E to 54th St E).

Road Construction

  • Final grading between 54th and 51st St E (including intersections)
  • Paving Asphalt base on phase II-a (54th to 51st St E) 
  • Pacing tree top soil for phase I (Between 58th and 54th St E)
  • Placing boulevard top soil for Phase II-a (54th to 51St E)
  • Placing foundation for lighting unit.
  • Adjusting/Raising Manholes for Phase I (58th to 54th St E)

September 24, 2019 Meeting Announcement

Meeting Announcement

The Department of Public Works will be holding informational meetings to address any questions that you may have about 34th Ave S project. The next meeting will be held on September 30, 2019 at Nokomis Library.

Nokomis Library 
5100 34th Ave S, Minneapolis MN 55417
September 30, 2019, 6:15 – 7:15 p.m.

See the full meeting announcement letter (September 23, 2019) from project engineer Menbere Wodajo.

September 20, 2019 Update

Work Completed in the Past Week

Road Construction

  • Completed work
    • 52nd intersection 
      • Pavement, curb & sidewalk removal
      • Storm and sanitary work
      • Center Point abandoned gas pipe removal
      • Lighting conduit installation
    • Water manhole reconstruction and subgrade correction at Wenonah
    • Bus pad and driveway placement between 54th and 52nd
  • Max has been working on subgrade correction at 52nd intersection and between 52nd and 51st.
  • Premier has been installing lighting conduit between 54th and 52nd St E.

Anticipated Work for the Next Week

Weekend Work (September 21, 2019)

  • Max and Ti-Zack (Max subcontractor) are tentatively scheduled to work on grading for curb & gutter, sidewalk and bus pad at 52nd intersection and between 52nd and 51st St E.

Work Next Week

  • 52nd intersection next week work
    • Complete grading
    • Place curb & gutter
    • Place sidewalk
  • Bus pad repair, mid-block of 58th and 56th St E
  • Between 54th and 51st
    • Sidewalk grading and pouring
    • Placing bus pad and driveway
    • Installing lighting conduit
    • Placing top soil  

September 16, 2019 Update

Meeting Announcement

The Department of Public Works will be holding informational meetings to address any questions that you may have about 34th Ave S project. The next meeting will be held on September 20, 2019 at Nokomis Library.

Nokomis Library 
5100 34th Ave S, Minneapolis MN 55417
September 20, 2019, 12:00 – 12:30 p.m.

See the full meeting announcement letter (September 16, 2019) from project engineer Menbere Wodajo.

September 13, 2019 Update

Work Completed in the Past Week

Road Construction

  • Max has been removing and preparing driveway between 54th and 52nd St E.
  • Ti-Zack has been installing curb between 54th and 52nd St E 
  • Premier has been installing lighting conduit between 54th and 52nd St E
  • Minnesota sod company, Max subcontractor has been placing sod between 58th and 54th St E

Utility Work

  • Center point: Completed lowering gas pipe between 54th and 51st St E

Anticipated Work for Next Week

Weekend Work (September 14, 2019)

  • Max will work on grading for bus pad, driveway.
  • Ti-Zack will work on preparing and forming for bus pad and driveways.

Road Closure

  • 52nd St E intersection is tentatively scheduled to be closed for 10 days starting Monday September 16, 2019. This closure is necessary in order to complete some of major construction activities at the intersection, such as remove concrete pavement and Sidewalk, install catch basins, subgrade preparation, install curb.  Please understand that the construction schedules are subject to change due to weather and unforeseen circumstances. 
  • 52nd intersection next week work
    • Remove pavement, curb & gutter and sidewalk
    • Remove abandoned gas pipe  
    • Storm and sanitary work 
    • Subgrade correction
    • Place Curb & Gutter
  • Between 54th and 51st
    • Place Driveway 
    • Install lighting conduit
    • Finish water manhole reconstruction and Subgrade correction at Wenonah intersection 
    • Prepare for sidewalk

September 6, 2019 Update

Work Completed in the Past Week

Road Construction

  • Max: Completed removing pavement, curb & gutter and sidewalk at 54th intersection; and has been working on Subgrade correction between 54th and 53rd St E and Installing top soil for Phase I (58th St to 54th St E)
  • Kusske (Max subcontractor): Completed sanitary reconstruction at 54th intersection; and has been working on water manholes reconstruction between 54th and 52st St E

Utility Work

  • Center point: Michaels (CenterPoint contractor) completed removing abandoned gas pipe at 54th intersection

Anticipated Work for Next Week

Weekend Work (Tomorrow, September 7, 2019)

  • Max will work on grading for curb and driveway.
  • Ti-Zack Max subcontractor will work on setting grade for curb & Gutter 

Utility work

CenterPoint will lower gas pipe at Wenonah intersection.

Road work

  • Subgrade correction at Wenonah intersection
  • 54th intersection and between 54th and 52nd St E
  • Curb and gutter placement
  • Driveway placement 
  • Bus pad placement

August 30, 2019 Update

Work Completed in the Past Week

Road Construction

  • Max has been working on subgrade correction between 52nd and 51st St E
  • Max has been working on installing top soil for Phase I (58th St to 54th St E)
  • Kusske Max subcontractor has been working on Catch basin installation and sanitary manhole reconstruction between 54th and 51st St E.

Utility Work

  • Xcel: Has been working on lowering the pipe at 53rd intersection.

Anticipated Work for Next Week

Road closure

  • 54th St E intersection is tentatively scheduled to be closed for 10 days starting Tuesday Sept 3rd, 2019. This closure is necessary in order to complete some of major construction activities at the intersection, such as remove concrete pavement and Sidewalk, install catch basins, subgrade preparation, install curb.  Please understand that the construction schedules are subject to change due to weather and unforeseen circumstances.

After hours work

On Wednesday Sept 4, 2019, Kusske Max subcontractor is planning to work up to 9:00 pm.

  • 54th intersection next week work
    • Remove pavement, curb & gutter and sidewalk
    • Subgrade correction
    • Storm and sanitary work 
  • Max will continue working on top soil placement for phase I
  • Driveway removal between 54th and 51st St E.

August 23, 2019 Update

Work Completed in the Past Week

Road Construction

  • Max has been working on subgrade correction between 52nd and 54th St E and 52nd and 51st St E
  • Kusske Max subcontractor completed fire hydrant relocation.
  • Kusske has been working on storm and sanitary structure improvement between 54th and 51st St E

Utility Work

  • CenterPoint Energy: Michaels, CenterPoint contractor has completed removing abandoned Gas pipe between 52nd and 51St E.

Anticipated Work for Next Week

Weekend Work

  • Tomorrow, August 24, Max Steiniger will continue working on subgrade correction.  between 52nd and 51st St E.

Road Closure

  • 34th Ave S from 52nd St E to 51st St E will be closed to all traffic on Wednesday Aug 28th, 2019. This closure will be only for one day and then will return to local traffic only. During this closure, all traffic will be detoured to designated detour route.  Please understand that this schedule is subject to change due to weather or unforeseen circumstances
  • Max will continue working on soil correction between 54th and 51st St E
  • Max Steiniger sub-contractor Kusske construction will continue working on installing underground utility pipe between 54th and 52nd St E.
  • CenterPoint will lower gas pipe as needed.  

August 16, 2019 Update

Work Completed in the Past Week

Road Construction

  • Max has completed pavement removal between 54th and 51st St E. 

Utility Work

  • CenterPoint Energy: Michaels, CenterPoint contractor has completed removing abandoned Gas pipe between 54th and 52nd E. 
  • US internet: IRONWOOD, US internet contractor is laying conduit behind sidewalk

Anticipated Work for This Week

Road Construction

  • Max will continue working on soil correction between 52nd and 54th St E and 52nd and 51st St E

Utility Work

  • Michaels CenterPoint contractor will keep working on removing abandoned Gas pipe between 52nd and 51st St E
  • Max Steiniger sub-contractor Kusske construction will start working on installing underground utility pipe. 

August 9, 2019 Update

Work Completed in the Past Week

Road Construction

  • Max has been removing pavement between 52nd and 54th St E. 
  • Max has been working on soil correction between 52nd and 53rd St E.

Utility Work

  • US internet: IRONWOOD, US internet contractor is laying conduit behind sidewalk
  • CenterPoint Energy: Michaels, CenterPoint contractor is working on removing abandoned Gas pipe between 52nd and 53rd St E. 

Anticipated Work for This Week

Road Construction

  • Max will continue working on soil correction between 52nd and 54th St E
  • Max will start removing pavement between 51st and 52nd St E 

Utility Work

  • Michaels CenterPoint contractor will keep working on removing abandoned Gas pipe between 52nd and 54th St E
  • Monday/Tuesday City Water will work on water main repair 53rd intersection.
  • IRONWOOD, US internet will keep working on drilling and laying conduit behind sidewalk

August 2, 2019 Update

Road Construction

  • Phase I (58th St E to 54th St E) is open for traffic.
  • Phase II-a (54th St E to 51st St) is closed to thru traffic.
  • Safety Sign (Max Subcontractor) have completed Installing temporary traffic control and detour for phase II-a (54th and 51th St E).  
  • Safety Sign (Max Subcontractor) have been removing existing signs.
  • Installation of Erosion control and tree protection is completed
  • Max have been removing pavement starting 52nd St E going south 
  • Premier have been installing light foundation between 56th and 58th St E

Anticipated Work for Next Week 

  • Max will continue removing pavement between 52nd St E and 54th St E 
  • Max will work on soil correction between 52nd St E and 54th St E 

July 29, 2019 Update (Meeting Announcement)

Meeting Announcement

The Department of Public Works will be holding informational meetings to address any questions that you may have about 34th Ave S project. The next meeting will be held on August 2, 2019 at Nokomis Library.

Nokomis Library 
5100 34th Ave S, Minneapolis MN 55417
August 2, 2019, 12:00 – 12:30 p.m.

See the full meeting announcement letter (July 29, 2019) from project engineer Menbere Wodajo.

July 26, 2019 Update

Road Construction

  • The first three lifts of asphalt placement are completed between 58th and 54th St E
  • Asphalt patching behind driveway is completed between 58th and 54th St E
  • Max have been working on preparing sidewalk subgrade/base between 56thand 58th St E.
  • Ti-Zack (Max Subcontractor) have been working on placing sidewalk between 55thand 58th St E.
  • Safety Sign (Max Subcontractor) have completed temporary striping between 54th and 58th St E  
  • Safety Sign (Max Subcontractor) have been working on installing sign foundation between 54th and 58th St E  
  • Premier have been working on installation of lighting conduit and foundation for lighting unit

Anticipated Work for Next Week

  • Weekend Work: Tomorrow, July 27, 2019

    • Ti-Zack (Max Subcontractor) will continue working on placing sidewalks between 58th and 54th St E. 
    • Safety sign (Max Subcontractor) will work on installing signs between 58th and 54th St E.

Phase II Update

  • Monday July 29, 2019
    • Phase I will be open to traffic
    • Phase II-a (54th to 51st St E )will be closed to thru traffic
    • Phase II-a pavement removal will begin.

July 23, 2019 Update (Meeting Announcement)

Meeting Announcement

The Department of Public Works will be holding informational meetings to address any questions that you may have about 34th Ave S project. The meetings will be held on July 26, 2019 at Nokomis Library.

Nokomis Library 
5100 34th Ave S, Minneapolis MN 55417
July 26, 3:00 p.m. – 4:00 p.m. and 4:00 p.m. – 5:00 p.m.

See the full meeting announcement letter (July 23, 2019) from project engineer Menbere Wodajo.

July 19, 2019 Update

Road Construction

  • Max completed subgrade correction between 54th and 56th St E
  • Valley Paving (Max subcontractor) have been paving the first three lifts of asphalt between 54th and 58th.
  • Valley have been working on patching behind driveway between 54th and 58th
  • Ti-Zack have been working on placing bus pad & driveway between 56th and 58th.
  • Premier have been working on installation of lighting conduit and foundation for lighting unit

Anticipated Work for Next Week

  • Between 56th and 58th
    • Remove and prepare east side Sidewalk and carriage walk.
    • Place concrete sidewalk & carriage walk
    • Continue working on installation of lighting conduit and foundation for lighting unit 
  • Between 54th and 56th
    • Placing sidewalk

Phase II Update

  • The first portion of Phase II will be from 54th to 51stSt E. Depending on the completion of this phase and private utility work, we might reconstruct 51st to 50th St E in 2019 construction.  
  • Phase II reconstruction (54th to 51st St E) is tentatively scheduled to begin on July 29. Please understand that this schedule is subject to change due to phase I substantial completion. 

See the full 34th Ave S Project Update (July 19, 2019) from project engineer Menbere Wodajo.

July 5, 2019 Update

Road Construction

  • Max have been working on grading between 56th and 58th St E.
  • Ti-Zack have been working on placing curb & gutter between 56th and 58th St E

Anticipated Work for Next Week 

  • Between 56th and 58th
    • Remove drive way and prepare the subgrade
    • Place new concrete Driveway
    • Continue roadway grading.
    • Continue placing concrete curb & cutter, sidewalk, carriage walk, bus pad.
    • Continue working on installation of lighting conduit and foundation for lighting unit 
  • Between 54th and 56th
    • subgrade correction

See the full 34th Ave S Project Update (July 5, 2019) from project engineer Menbere Wodajo.

June 28, 2019 Update

Road Construction

  • 58th intersection
    • Grading is completed
    • Curb & Gutter and bus pad is completed.
    • Is open for traffic.
  • Kusske construction have completed Sanitary and Storm main line work between 56th St E and 58th St E. 
  • Max have been working on grading between 56th and 58th.
  • Premier have been working on lighting conduit and foundation for lighting unit between 56th and 58th.

Anticipated Work for Tomorrow and Next Week

  • Weekend work:
    • Tomorrow, June 29, Max Steiniger will continue working on grading between 56th and 58th 
  • Between 56th and 58th
    • Continue grading
    • Place concrete curb & cutter, sidewalk, carriage walk, bus pad.
    • Remove drive way
    • Preparing subgrade for Driveway
    • Continue working on installation of lighting conduit and foundation for lighting unit
  • No work on July 4th and July 5th

See the full 34th Ave S Project Update (June 28, 2019) from project engineer Menbere Wodajo.

June 14, 2019 Update

Road Construction

  • Kusske construction have completed private sanitary connection between 56th St E and 58th St E.
  • Ti-Zack have been placing concrete Driveway apron, Sidewalk, Bus pad, Carriage walk and Curb and gutter
  • Premier Electrical have been working on installing foundation for lighting unit and conduit behind curb 54th to 58th

Anticipated Work for Tomorrow and Next Week

Road Closure

  • 58th St E intersection will be closed on Monday. This closure is necessary in order to complete some of major construction activities at the intersection, such as remove concrete pavement and sidewalk, install Storm and Sanitary main line, install catch basins, subgrade preparation, install curb and gutter as well as pas pad. Please understand that the construction schedules are subject to change due to weather and unforeseen circumstances.
  • Placing the first three lifts of asphalt between 54th and 56th (including 56th intersection) is tentatively scheduled for Thursday June 20.
  • Complete sanitary and storm main line and work on catch basin at 58th intersection.
  • Continue working on installation of lighting conduit and foundation for lighting unit
  • Continue working on placing Driveway, Sidewalk, Bus pad, Carriage walk and Curb and gutter

See the full 34th Ave S Project Update (June 14, 2019) from project engineer Menbere Wodajo.

June 7, 2019 Update

Road Construction

  • Grading between 55th and 56th St E is completed
  • Kusske construction have been working on storm and sanitary main and as well as private connection between 56th St E and 58th St E.
  • Premier Electrical have been working on installing foundation for lighting unit and conduit behind curb.
  • Potholing at 53rd & 54th St E intersection is completed  
  • Max Steiniger have been working on grading driveways between 54th and 56th St E

Anticipated Work for Tomorrow and Next Week

Weekend Work

  • Ti-Zack, Max Steiniger sub-contractor is planning to pour curb and gutter and also bus pad tomorrow
  • Kusske construction, Max Steiniger sub-contractor will keep working on sanitary main and private connection tomorrow

Road Closure

  • 58th St E intersection is tentatively scheduled to be closed for 10 days starting Thursday June 13, 2019. This closure is necessary in order to complete some of major construction activities at the intersection, such as remove concrete pavement and Sidewalk, install catch basins, subgrade preparation, install curb.  Please understand that the construction schedules are subject to change due to weather and unforeseen circumstances.
  • Drive way placement, between 54th St E and 56th St E,
  • Complete storm work between 56th and 58th St E
  • Finish sanitary sewer main and service work between 56th and 58th St E. 
  • Concrete curb & gutter placement between 54th and 56th St E
  • Sidewalk grading and placement between 54th and 56th St E
  • Remove driveway between 56th St E to 58th St E
  • Continue working on installation of lighting conduit and foundation for lighting unit.
  • Remove pavement, curb & gutter and sidewalk at 58th intersection

CenterPoint

  • CenterPoint Energy's utility contractor Michaels have finished removing abandoned gas pipe for phase I (54th St E to 58TH St E)

See the full 34th Ave S Project Update (June 7, 2019) from project engineer Menbere Wodajo.

May 31, 2019 Update

Road Construction

  • Grading between 55th and 56th St E will be completed today
  • Premier Electrical, Max Steiniger sub-contractor have been working on installing lighting conduit behind curb.
  • Kusske construction have been working on storm sewer main between 56th St E and 58th St E. 
  • City water division completed relocating fire hydrant at NW corner of 34th & 58th intersection (backfilling will be completed today as well). 

Anticipated Work Next Week

  • Drive way grading and placement, between 54th St E and 56th St E, is tentatively scheduled to start on June 4th
  • Potholing at 53rd & 54th St E intersection for Xcel ducts & pipes is tentatively scheduled on Tuesday June 4th, (A segment of the road will be closed for a few hours, but no measure traffic impact is anticipated for this activity). 
  • Complete storm work between 56th and 58th St E
  • Work on sanitary sewer main and service work between 56th and 58th St E. 
  • Resume concrete curb & gutter placement between 54th and 56th St E
  • Sidewalk grading and placement between 54th and 56th St E
  • Remove driveway between 56th St E to 58th St E
  • Lighting conduit installation.

Please understand that the construction schedules are subject to change due to weather and unforeseen circumstances.

CenterPoint

  • CenterPoint Energy's utility contractor Michaels have finished removing abandoned gas pipe for phase I (54th St E to 58TH St E)

See the full 34th Ave S Project Update (May 31, 2019) from project engineer Menbere Wodajo.

Open House Notification

The Department of Public Works will be holding a series of public informational meetings to address any questions that you may have about 34th Ave S project. The meetings will be held every other Friday, starting May 31, 2019 at 11:00 a.m. The first two meetings will be held at the following location and dates:

SASSY SPOON
5009 34th Ave S, Minneapolis MN 55417
May 31, 11:00 a.m. -12:00 p.m.

SASSY SPOON
5009 34th Ave S, Minneapolis MN 55417
June 14, 11:00 a.m. -12:00 p.m.

See the informational meeting invitation from project engineer Menbere Wodajo for more details.

May 24, 2019 Update

  • Max Steiniger sub-contractor Ti-Zack pour concrete curb & gutter between
    • 54th St E and 55th St E on both side
    • 55th St E and 56th St E east side
  • 56th intersection
    • Grading completed.
    • Curb poured except SE corner
    • Open for Traffic
  • Between 56th St E and 58th St E, Kusske construction have been continuing work on sanitary sewer main and service work between. 

Anticipated Work next week

  • Complete roadway grading between 55th and 56th St E
  • Continue concrete curb & gutter placement between 55th and 56th St E
  • Begin drive way grading between 54th St E and 56th St E
  • Continue sanitary sewer main and service work between 56th St E and 58th St E. 
  • Remove driveway between 56th St E to 58th St E
  • Begin roadway grading between 56th St E to 58th St E
  • Relocate Fire hydrant at NW corner of 34th & 58th intersection.
  • Potholing at 54th & 53rd St E intersection for Xcel ducts & pipes. (A segment of the road will be closed for a few hours, but no measure traffic impact is anticipated for this activity). 
  • Please understand that the construction schedules are subject to change due to weather and unforeseen circumstances.

CenterPoint

  • CenterPoint Energy's utility contractor Michaels have finished removing abandoned gas pipe for phase I (54th St E to 58TH St E)

See the full 34th Ave S Project Update (May 24, 2019) from project engineer Menbere Wodajo.

May 17, 2019 Update

  • Max Steiniger sub-contractor Kusske construction have been continuing work on sanitary sewer main and service work between 56th St E and 58th St E. 
  • Max Steiniger have been continuing working on subgrade preparation between 54th St E and 56th St E

56th intersection 

  • Kusske construction has completed sewer except SE corner.
  • Max Steiniger will finish Grading today

Local Traffic Access

  • 56th St E intersection have been closed to thru traffic. But during working days when sewer crews work on sanitary sewer main and service work between 56th and 58th St E, access will be available from 58th on 34th Ave up to the equipment spread and one lane access will be available at SE corner of 56th St intersection.

Anticipated Work for tomorrow and next week

  • Concrete Curb & Gutter placement at 56th intersection is scheduled for tomorrow Saturday, May 18 (Max Steiniger sub-contractor Ti-Zack).
  • Continuing Sanitary sewer main and service work between 56th St E and 58th St E. 
  • Concrete Curb & Gutter placement between 54th St E and 56th St E 
  • Removing driveway between 58th St E to 56th St E

See the full 34th Ave S Project Update (May 17, 2019) from project engineer Menbere Wodajo.

May 10, 2019 Update

  • 56th St E Intersection will be closed for 10 days from Monday May 13 to Wednesday May 22nd. This closure is necessary in order to complete some of major construction activities at the intersection, such as remove concrete pavement and Sidewalk, install catch basins, subgrade preparation, install curb.  Please understand that the construction schedules are subject to change due to weather and unforeseen circumstances.
  • Max Steiniger sub-contractor Kusske construction completed 56th Intersection Sanitary work and will keep working between 56th St E and 58th St E.
  • Max Steiniger have been continuing working on
    • Subgrade preparation between 54th St E and 55th St E
    • Removing driveway between 58th St E to 56th St E

See the full 34th Ave S Project Update (May 10, 2019) from project engineer Menbere Wodajo.

May 9, 2019 Update

  • 56th St E Intersection Closure 
    • 56th St E will be closed to traffic for 10 days from Monday May 13 to Wednesday May 22nd.

See the full 34th Ave S Project Update (May 9, 2019) from project engineer Menbere Wodajo.

May 6, 2019 Update

  • 56th St E Intersection
    • Will be closed on Monday May 6, 2019 for sanitary main line installation.
    • Will be open on Tuesday. Please understand that the construction schedules are subject to change due to weather and unforeseen circumstances.
  • Next week Max Steiniger will begin working on grading the road between 54th St E and 56th St E.

See the full 34th Ave S Project Update (May 6, 2019) from project engineer Menbere Wodajo.

April 18, 2019 Update

  • Max Stinger (the Contractor for 34th Ave S) has begun to construct 34th Ave S Phase I (58th St E to 54th St E) on Monday April 15th. 
  • Traffic control and detours are in place for phase I.
  • 34th Ave from 58th St E to 54th St E will be open only to local traffic but closed to thru traffic.
  • Underground utility work will follow removal of pavement, Curb and Gutter. 
  • Center Point & Century link will work in conjunction with Contractor to mitigate any conflict with proposed city infrastructure in the corridor.
  • In addition, Center Point will install new proposed pipe outside Phase I (they will reach out the community) .    
  • Once the removal and underground utility work is complete, the new asphalt pavement can be placed. If the approach to your driveway is in the project construction limits, we will notify you in advance of placing your new driveway approach 
  • Typical working hours: 7am to 6pm Monday thru Friday.
  • Phase I is estimated to be substantially completed with new pavement by first week of July. Please understand that the construction schedules are subject to change due to weather and unforeseen circumstances.

See the full 34th Ave S project update from project engineer Menbere Wodajo.

March 8, 2019 Update

We plan tentatively to start construction on April 15, 2019.

June 4, 2018 Update

May 1, 2018 Update

March 13, 2018 Update

Project is now planned for 2019. A Public Hearing is tentatively set for June 5, 2018.

March 24, 2017 Update

The staff-recommended Project Layout (Part 1 and Part 2) was approved at the March 24th, 2017 City Council Transportation and Public Works Committee Meeting.

March 2, 2017 Update

The project's Preliminary Layout (Part 1 and Part 2) is now available.

Project Contacts

Menbere Wodajo, Construction Engineer; [email protected] or 612-673-3716

Email Updates
To sign up for updates or to access your subscriber preferences, please enter your contact information below.

 

Last updated Jul 10, 2020

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-263-6850.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

Public Works  ©1997-2020 City of Minneapolis, MN

CONNECT

311 call center

311 TTY relay service

City of Minneapolis Facebook City of Minneapolis Twitter City of Minneapolis YouTube ChaNNEL Minneapolis 311 Watch Minneapolis City Council TV City of Minneapolis LinkedIn

Minneapolis, City of Lakes logo