Plymouth Ave N Reconstruction

The City of Minneapolis is planning to reconstruct approximately 0.5 miles of Plymouth Avenue North between Xerxes Avenue North and Penn Avenue North.  The project will replace aging pavement and improve the right-of-way for all users and modes of travel. This project provides an opportunity to incorporate ADA compliant curb ramps, add boulevards with trees, address sidewalk obstructions, and improve the existing bicycle facility. 

For more information, see below or download the Plymouth Ave N Project Fact Sheet.

 Plymouth Ave N Reconstruction 2021 map

Project status

Project Status: Design

Recommended design concept

The Public Works recommended conceptual design for the Plymouth Avenue project was approved by the Policy & Government Oversight Committee (POGO) of the City Council on Wednesday, April 8, 2020 and by the full City Council on Friday, April 10, 2020. More information and meeting agendas are available on the City's website.

The draft design concept for the Plymouth Avenue Street Reconstruction Project includes sidewalks and wider boulevards on both sides of the street, protected bike facilities on both sides of the street (behind the curb at sidewalk level), bump outs or curb extensions and raised crosswalks at most sidestreet intersections, and on-street parking on one -side of the street.

This design will improve safety for all users, greatly improve the pedestrian and bicyclist experience, add space for plantings and improved stormwater treatment, and it will also maintain vehicle access throughout the corridor.

Project details

Project Type

This project includes full reconstruction of the entire right-of-way and will include new sidewalks, ADA pedestrian ramps, furnishing zones or boulevard space, bicycle facilities, curb and gutter, and utility improvements. The project will also include new signage, and new pavement markings.

Project Limits

Approximately 0.5 miles of Plymouth Avenue North between Xerxes Avenue N and Penn Avenue N.

Timeline

Summer 2019 – Spring 2020

Spring 2020

Spring - Fall 2020

Spring 2021

Traffic impacts

Construction is anticipated to begin in 2021. During construction, residents, businesses, and visitors may expect traffic detours, noise, vibration, and dust in work areas. In addition, temporary impacts such as lane restrictions, intersection reductions, parking restrictions or revised pedestrian and bicycle routes may be expected during construction. Property access will be maintained throughout construction. Specific construction staging and traffic detour information will be posted here as the project gets closer to construction.

Project meetings

Open House #2

Tuesday, December 3, 2019
6:00 - 7:00 p.m.
Urban Research and Outreach-Engagement Center (UROC), Room 105
2001 Plymouth Ave N
Minneapolis, MN 55411

Open House #1

Tuesday, June 25, 2019, 6:00-7:00 p.m.
Urban Research and Outreach-Engagement Center (UROC), Room 105
2001 Plymouth Ave N
Minneapolis, MN 55411

Contacts

Alebel Mehari, Project Engineer; 612-673-3602 or [email protected]

Dan Edgerton, Project Planner; 612-207-5722 or [email protected]

 

Last updated Sep 10, 2020

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-263-6850.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

Public Works  ©1997-2020 City of Minneapolis, MN

CONNECT

311 call center

311 TTY relay service

City of Minneapolis Facebook City of Minneapolis Twitter City of Minneapolis YouTube ChaNNEL Minneapolis 311 Watch Minneapolis City Council TV City of Minneapolis LinkedIn

Minneapolis, City of Lakes logo