Bryant Ave S Street Reconstruction
In 2022, the City of Minneapolis plans to reconstruct the street on Bryant Ave S from Lake St to 50th St W.
For more information, view and download the Bryant Ave S Reconstruction Fact Sheet.
December 10, 2020 virtual open house recording
The City of Minneapolis hosted the second virtual open house for the Bryant Avenue Reconstruction project. The purpose of the meeting was to share project updates and solicit input from the public on draft design concepts for the reconstruction of Bryant Avenue S.
Please see the below links to view the presentation’s live recording and review a report of questions and comments from the presentation.
Meeting resources
- View the draft drawing of the full Bryant Ave corridor
- View information on the Lyndale Ave S draft transit proposal
- See a detailed breakdown of proposed on-street parking by block
- View the Bryant Ave: Other options context booklet
- Provide feedback on the draft concept design through our:
The survey and map are available through March 1, 2021.
Virtual group discussions
For more interactive review and live conversation about the draft concept design, the City is also hosting smaller virtual group discussions for different parts of the corridor. Register for one of these discussions below. Once you’ve registered, we’ll email you a meeting invite with the link to join the meeting.
If you cannot make these dates, but still would like to have a one-on-one or small group conversation with project staff, please email us at [email protected] and we can set up a time that work for you.
We hope you can join us!
Meeting registration
January 12, 2021 | 12 - 1 p.m.
January 12, 2021 | 7 - 8 p.m.
January 13, 2021 | 12 - 1 p.m.
January 13, 2021 | 7 - 8 p.m.
January 14, 2021 | 12 - 1 p.m.
January 14, 2021 | 7 - 8 p.m.
Notice: These meetings are intended for smaller groups. Each will maintain a 30-attendee limit. Additional meetings will be scheduled to accommodate any meeting overflows.
What we've been working on
Stakeholder engagement
- We’ve introduced and shared information about the project with over 40 businesses along the corridor, three neighborhood groups, and many corridor residents
- Haven’t connected with us yet? Please contact us (contact information below).
Green infrastructure analysis
- A goal of this project is to use green infrastructure to collect and treat stormwater runoff. To meet this goal, we’ve been working to identify the locations along the corridor where the City has opportunities to implement green infrastructure and where green infrastructure would have the highest positive impact.
- To learn more about green infrastructure opportunities on Bryant Ave S, view our green infrastructure opportunities fact sheet.
Encroachment review
- Along Bryant Avenue the City’s right of way is 60 feet wide, but within this right of way there are many encroachments, such as existing retaining walls, stairs, trees, and landscaping, that limit the ability to use the full 60-foot right-of-way.
- We have reviewed the encroachments along the entire corridor and identified the blocks where we think constructing out to the full 60 feet is reasonable. Overall, we’ve found there are 5 blocks with limited encroachments, meaning the entire 60 feet of public right of way is available for this project to use.
- We’ve also found that at business nodes, generally, there is 60 feet of public right-of-way available to use.
Lyndale Ave S traffic patterns analysis
- As part of this work, we are exploring what it would look like to move transit from Bryant Ave S to Lyndale Ave S to balance the space required for all users in the corridor while meeting the project goal of supporting existing and future transit service in the area.
- We’ve found that most intersections on Lyndale Ave S generally operate at an acceptable level today and we can expect this to continue at most intersections into the foreseeable future.
Project goals
- Improve pedestrian safety and access
- Create an All Ages and Abilities bicycle connection in the area
- Support existing and future transit service in the area
- Use green infrastructure to collect and treat stormwater runoff
- Accommodate business deliveries and customer access
Project timeline
The Bryant Ave S project is currently programmed to begin construction in 2022; however, as a part of the upcoming Capital Improvement Plan (CIP) cycle, Public Works will recommend moving the project forward in the CIP so the reconstruction can begin in 2022. The conceptual design phase of the project, including stakeholder engagement, will begin in early 2020.
May 12, 2020 virtual open house
Public Works held a virtual open house on May 12, 2020 to kick off the project. A full recording, a transcript of the questions received during the event, and answers to frequently asked questions are all available below:
- Virtual Open House Recording
- Presentation Slides
- Transcript of Questions Received
- Frequently Asked Questions
We also have a shorter presentation discussing similar materials that you can listen to:
Project survey and feedback map
Thank you for taking our survey and providing comments on the interactive map. Please see the below summary of feedback received throughout our initial project engagement. The below summaries include an overview of feedback received across all three online engagement forums, including the Live Open House, Bryant Ave South Wiki Map and Survey. Also included below are the appendices with detailed engagement summaries and graphics (Appendix A) plus the raw comments received from the online survey (Appendix B).
Summary Appendix A (detailed engagement summary)
Summary Appendix B (Raw survey responses)
Project updates
Sign up for email updates by entering your email below.
Project documents
2018 Bryant Ave S Existing Conditions Study
2020 Existing Conditions Factsheet
2020 Existing Conditions Video Presentation
2020 Existing conditions presentation slides
Bryant Ave S On-Street Parking Trends
Contact us
Liz Heyman, Senior Transportation Planner
612-673-2460
[email protected]
Trey Joiner, Associate Transportation Planner
612-673-3614
[email protected]
Last updated Dec 15, 2020