Concrete Streets Rehabilitation

The purpose of the Concrete Streets Rehabilitation Program is to extend the life of some concrete city streets. This program is similar to the Asphalt Pavement Resurfacing Program with the objective to improve and maintain the roadway infrastructure. The goal is to target concrete streets that with proper concrete repair will extend the street’s life to improve ride quality and support neighborhood livability.

Program Background

An Explanation of Concrete Rehabilitation

Concrete streets generally deteriorate over time as water and salt enter joints and cracks. Poor drainage, underlying soil condition, and higher traffic volumes can accelerate the deterioration. The repair of concrete primarily consists of saw cutting, removing and replacing concrete joints that have deteriorated and other pavement distresses. Other repair techniques include removal and replacement of concrete panels if it is determined the condition of the concrete does not warrant salvaging the panel pavement. Other improvements within the project limits include upgrades to select pedestrian ramps, replacement of select curb and gutter, and a diamond grind resurfacing of the street pavement. For this type of work, it is anticipated that less than 25% of the pavement will be replaced. Concurrent with the street work, utility improvements will be completed associated with gas, water and sewer.

Project Areas

Waite Park (2019-2020)

Concrete street rehabilitation will be continued in the Waite Park neighborhood in 2019 and 2020. These concrete streets were constructed in 1967 and 1968 and are good candidates for concrete repair and resurfacing.

 2019 Waite Park Map

Project Status

Project Status: Construction

Schedule

The City of Minneapolis’ concrete rehab project will start tentatively on August 14, 2019.  The City will start the project in the SE portion of the project.  It is anticipated that a portion of the project will be completed in 2019, and the remainder will be completed in 2020.

Before the construction activities start, the street will be marked out for repair. As the construction date gets closer, advance notice signage will be placed on the street.  Notices will be delivered to residents whose block will start construction in advance of the work.  Additionally, if a driveway will be directly impacted, the contractor will notify you in advance of the work. They will leave a flyer at your front door, so please be sure to check this area regularly if work is taking place on your block. The advance notice for driveway work will be given the day before driveway impacts will begin.

Additionally, CenterPoint Energy will perform utility work either before or concurrent with street reconstruction.  They are upgrading gas mains and services. For more information on CenterPoint Energy's work, please visit CenterPoint Energy's Waite Park project page.

Traffic Impact

When the City’s contractor is actively working on a block, they will close the block to through traffic. If there are no driveways on a block, they may keep the block closed to traffic until all of the work is complete on the block. If your block is being worked on, please consider parking in your alley (if present) or on an adjacent street. Please give yourself extra time and be prepared to go in an alternate direction than intended. If your driveway is impacted, please be prepared to not use the driveway for a few days.  The contractor will work to minimize inconveniences, but there will be equipment and people that will need to work on the street to make these improvements. 

Additionally, due to the nature of concrete, it can take up to several days to gain the strength that it needs to allow traffic to drive on it.  This means that there will be times when there are lane closures and no one will be actively working on the street. If traffic drives on new concrete too soon, it could lead to cracking of the new pavement.  This could require the work activities to be re-done and additional inconveniences.  Emergency vehicles always have priority through our construction projects, and they will not hesitate to do what they need to do to respond to an emergency.

If you have special mobility concerns, such as handicapped parking or Metro Mobility pickups and drop-offs, please reach out to the project team so we can work with you to maintain your transportation access.

Updates

October 14, 2020

Work this week

Wednesday, October 14

  • Sawing and sealing concrete that was poured 2019 on Ulysses St NE between 33rd Ave NE to St Anthony Parkway

Thursday, October 15

  • Sawing and sealing concrete that was poured 2019 on Hayes St NE between 33rd Ave NE to St Anthony Parkway

Friday, October 16

  • Sawing and sealing concrete that was poured 2019 on Garfield St NE between 33rd Ave NE to St Anthony Parkway.

Work anticipated for next week

Monday, October 19

  • Sawing and sealing concrete that was poured 2020 on Tyler St NE between St. Anthony Parkway to 35th Ave NE

Tuesday, October 20

  • Sawing and sealing concrete that was poured 2020 on Polk St NE between St Anthony Parkway to 35th Ave NE and from 36th Ave NE to  37th Ave NE

The project will be completed by 3rd week in October.

October 7, 2020

Work this week

Tuesday, October 6

  • Sawing and sealing through out project as well as restoration

Wednesday, October 7

  • Warranty work removals and concrete pouring on 34th Ave NE Tyler St NE and Taylor St NE

Thursday, October 8

  • Sawing and sealing continuing through out project

Friday, October 9

  • Final concrete pour curb and parking panels Taylor St NE between 36th Ave NE and 35th Ave NE, 32nd Ave NE ped ramp NW quad.

Work anticipated for next week

Monday, October 12

  • Sawing and sealing continuing as well as restoration

Tuesday, October 13

  • Project complete.

September 30, 2020

Work this week

Tuesday, September 29

  • Concrete pouring paving 31st Ave NE between Fillmore St NE and Buchanan St NE south side
  • Diamond grinding started Monday on Tyler St NE between 32nd Ave NE to 35th Ave NE and from 36th Ave NE to 37th Ave NE
  • Next Polk St NE  between 32th Ave NE to 37th Ave NE

Wednesday, September 30

  • Concrete pour paving 31st Ave NE between Fillmore St NE and Buchanan St NE north side including intersection and ped ramps NW quad, SW quad and SE quad.
  • Diamond grinding on 34th Ave NE and 32nd Ave NE.

Thursday, October 1

  • Concrete pouring finishing up ped ramps With that major concrete pouring will be complete.

Friday, October 2

  • Diamond grinding on Hollywood Ave NE including Hayes St NE and Cleveland St NE will continue and possibly finishing up.

Work anticipated for next week

Monday, October 5

  • Warranty work throughout the CPR project will start.

September 23, 2020

Work this week

Tuesday, September 22

  • Concrete pouring paving

  • 31st Ave NE between Fillmore St NE and Buchanan St NE  southside

Wednesday, September 23

  • Concrete pouring Ped ramps

  • 31st Ave NE and 31st Ave NE and Lincoln St NE SW Quad and 32nd Ave NE and Polk St NE NE Quad

  • Street cleaning Hollywood Ave NE, Fillmore St. NE and 34th Ave NE. 31st Ave between Lincoln St. NE and Buchanan St. NE.

  • Partial marking and milling Fillmore Ave NE between 36th Ave NE to R/R crossing, 34th Ave NE between Tyler St NE and Central Ave NE and Hollywood Ave NE between Hayes St NE and Cleveland St NE. 31st Ave NE between Lincoln St NE and Buchanan St NE.

Thursday, September 24

  • Partial marking and milling Fillmore St NE, 34th Ave and Hollywood Ave NE. Sawing and sealing Ulysses St NE.

Friday, September 25

  • Prepping partials. Restoration through out entire project.

Work anticipated for next week

Monday, September 28

  • Pouring partials

  • Diamond grinding starting Tyler St NE between 32nd Ave NE to 35th Ave NE 

  • Polk St NE between 34th Ave to 35th Ave NE continuing 36th Ave NE to 37th Ave NE. Tyler St NE between 37th Ave to alley. 31st Ave NE between Lincoln St NE and Buchanan St NE.

Tuesday, September 29

  • Concrete pouring paving 31st Ave NE between Fillmore St NE to Buchanan St NE north lane.

September 16, 2020

Work this week

  • Tuesday, September 15
    • Finished pouring paving on 32nd Ave NE at Polk St. NE Southland. Also included intersection,  ped ramp landing and curb section.
    • Concrete pouring on Fillmore St NE between R/R tracks and 36th Ave NE 2 Loads placed.
    • Curb and gutter placed at 31st Ave NE between Fillmore St NE and Buchanan St NE both sides north and south.
    •  Concrete removals on Hollywood Ave NE between Hayes St NE and Cleveland St NE.
  • Wednesday, September 16
    • Continuing removal and prep on Hollywood Ave NE
  • Thursday, September 17 
    • Afternoon concrete pouring on Fillmore St NE between 36th Ave NE and R/R tracks.
  • Friday, September 18
    • Concrete pouring on Hollywood Ave NE between Hayes St NE and Cleveland St NE

Work anticipated for next week

  • Monday, September 21
    • Concrete paving pouring on 31st Ave NE between Buchanan St NE and Fillmore St. NE. Milling partials depths.
  • Tuesday, September 22
    • Pouring partials.

September 9, 2020

Work this week

  • Tuesday, September 8
    • Curb and gutter 32nd Ave NE between Taylor St NE and Polk St NE north and south side.
    • Partials poured 32nd Ave NE between Polk St and Central Ave NE. 33rd Ave NE corners of Polk St NE and Tyler St NE. 34th Ave NE between Taylor St NE and Tyler St NE.
    • Removal ped ramp 36th Ave NE and Fillmore St. NE.
    • Street panels removed on Fillmore St NE.
  • Wednesday, September 9
    • Reworking subgrade on 31st Ave NE between Pierce St NE and Fillmore St. NE. Also removals continue on 31st Ave NE between Pierce St. NE and Lincoln St. NE.
    • Removals starting on Hollywood Ave NE between Hayes St NE and Cleveland St NE.
    • Pour started on 32nd Ave NE paving but was rained out after first load of concrete. Will continue Thursday 9/10/2020.
  • Thursday, September 10
    • Paving pour continues on 32nd Ave NE between Taylor St NE and Polk St NE north lane.
    • Concrete pouring ped ramps 33rd Ave NE and Polk St NE quad SW and ped ramp on 36th Ave NE and Fillmore St. NE quad NE and Hollywood Ave NE between Hayes St NE and Cleveland St NE.
  • Friday, September 11
    • Completing concrete pouring on Hollywood Ave NE between Hayes St NE and Cleveland St NE. Also concrete pour on 31st Ave NE between Buchanan St NE and Lincoln St. NE.

Work anticipated for next week

  • Monday, September 14
    • Curb and gutter 32nd Ave NE between Fillmore St NE and Pierce St NE north and south side.
    • Concrete pouring at R/R crossings at Polk St NE and Fillmore St. NE north and south sides of crossings.

September 3, 2020

Work this week

  • Tuesday, September 1, 2020: Concrete pouring on 32nd Ave NE between Polk St NE and Central Ave NE northside; backfilling using sand and class#5 on 32nd Ave NE between Taylor St NE and Polk St NE.
  • Wednesday, September 2, 2020: Concrete pouring on 34th Ave NE between Taylor St NE to Tyler St NE northside; ped ramps on 33rd Ave NE and Polk St NE Quads SW and SE, 34th Ave NE and Tyler St NE Quad SE, 32nd Ave NE and Tyler St NE  Quad SW, 33rd Ave NE and Tyler St NE Quad SW, Intersection panel Quad SW.
  • Thursday, September 3, 2020: Street cleaning followed by marking partials. Removals starting 31st Ave NE  between Johnson St NE and Fillmore St. NE
  • Friday, September 4, 2020: Partial depth milling and prepping

Work anticipated for next week

  • Monday, September 7, 2020: Holiday
  • Tuesday, September 8, 2020: Pouring partials

August 27, 2020

Work this week

  • Tuesday, August 25, 2020: Removals 33rd Ave NE ped ramp Polk St NE SE quad; 33rd Ave NE ped ramp Tyler St NE; prepare for concrete pouring
  • Wednesday, August 26, 2020: Poured concrete 32nd Ave NE Polk St NE to Central Ave NE portions of full depth; R/R crossing Polk St NE eastside North and South; R/R crossing Fillmore St NE eastside North and South.
  • Thursday, August 27, 2020: Finish pouring concrete on 34th Ave NE between Taylor St NE and Central Ave NE southside; 33rd Ave NE and Polk St NE ped ramp SE quad and 33rd Ave NE and Tyler St NE ped ramp SE quad; concrete pouring 32nd Ave NE and Tyler ped ramp SE quad.
  • Friday, August 28, 2020: No concrete poured; concrete removal 31st Ave NE between Johnson St NE and Fillmore St NE

Work anticipated for next week

  • Monday, August 31, 2020: Start reconditioning sub grade on 32nd Ave NE between Taylor St NE and Polk St NE; start removals northside 34th Ave between Taylor St NE to Central Ave NE; removals northside 32nd Ave NE between Polk St NE and Central Ave NE
  • Tuesday, September 1, 2020: Removals at R/R crossing westside of Polk St NE and Fillmore St. NE North and South.

August 19, 2020

Work this week

  • Tuesday, August 18, 2020: Prepping partial depths; Tyler St NE partials done; Polk St NE patrials done; Hayes St NE partials 1/2 done; Hollywood Ave NE 1 block remain; removals began 32nd Ave NE from Taylor St NE to Central Ave NE
  • Wednesday, August 19, 2020: Prepping partial depths; Hayes St NE parials done; Hollywood Ave NE done; continuing removals 32nd Ave NE from Taylor St NE to Central Ave NE
  • Thursday, August 20, 2020: Pouring partials; Tyler St NE between 37th Ave NE to alley; Polk St NE between 37th Ave NE to 36th Ave NE; Hayes St between 37th Ave NE to Hollywood Ave NE; Hollywood Ave NE to Johnson St. NE; removals continue on 32nd Ave NE
  • Friday, August 21, 2020: Removals to start on 34th Ave NE from Taylor St NE to Central Ave NE

Work anticipated for next week

  • Monday, August 24, 2020: Preparation to pour concrete on 32nd

August 12, 2020

Work this week

  • Tuesday, August 11, 2020: Concrete poured on Polk St. NE between 36th Ave NE and 37th Ave NE; ped ramp and sidewalk Hollywood Ave NE and Hayes St. NE. NW Quad; Ped ramp landing 37th Ave NE and Hayes St NE SW Quad; ped ramp landing 37th Ave NE and Tyler St. NE SE Quad; and finished prep on Tyler St NE between 37th Ave NE to the alley.
  • Wednesday, August 12, 2020: Concrete poured on Tyler St NE between 37th Ave NE and alley; 27.75 Cu Yds placed before (Rain Out)
  • Thursday, August 13, 2020: Finish pouring concrete  on Tyler St NE and move to Hayes St NE and Hollywood Ave NE; more concrete poured on Hollywood Ave NE and more removals.
  • Friday, August 14, 2020: No concrete work; milling partials through out job

Work anticipated for next week

  • Monday, August 17, 2020: Concrete removals on 32nd Ave NE between Tyler St. NE and Central Ave NE
     

August 5, 2020

Work in the past week

  • Tuesday, August 4, 2020: Concrete pour Polk St NE between 36th Ave NE and 37th Ave NE. Righthand side.
  • Wednesday, August 5, 2020: Concrete removal on Tyler St NE Righthand side between 37th Ave NE to dead end. Started sawing concrete on Hayes St NE between 37th Ave NE and Hollywood St NE; also sawing on Hollywood between Johnson St and Cleveland St NE
  • Thursday, August 6, 2020: Concrete removal on Hayes St NE and Hollywood Ave NE
  • Friday, August 7, 2020: Concrete pour Tyler St. NE , Hayes St  NE and Hollywood Ave NE

July 29, 2020

Work in the past week

  • Restoration with top soil, seed, and blankets is in progress throughout project.
  • Monday, July 27, 2020: Finished pouring full depth repairs on Tyler St NE; starting milling particals on Polk St NE and Tyler Ave NE.
  • Tuesday, July 28, 2020: Finished pouring ped ramps Polk St NE rand Tyler St NE both on 33rd Ave NE; started jackhammering particals Tyler St NE and Polk St NE
  • Wednesday, July 29, 2020: Started pouring partials on Tyler St NE; jackhammering partials on Polk St NE
  • Thursday, July 30, 2020; Start milling partials on Polk St NE  between 34th Ave NE and 35t h.c Ave NE  jackhammering to follow; start saw cutting o the Polk St. NE between 36th Ave NE and 37th Ave NE and Tyler St NE to follow.
  • Friday, July 31, 2020: Start pouring partials on Polk St NE between 32nd Ave and 35th Ave NE

Work anticipated for next week

  • Monday, August 3, 2020: Start removals on Polk Ave NE between 36th Ave NE and 37th Ave N Tyler St NE to follow.
     

July 21, 2020

Work in the past week

  • July 21, 2020: No work (rain out)
  • July 22, 2020: Concrete pouring will continue on Polk St. NE between 34th Ave NE and 35th Ave NE northbound; removals will continue on Tyler St NE southbound between 35th Ave NE to 32nd Ave NE
  • July 23 and 24, 2020: Concrete will be poured on Tyler St. NE southbound between 35th Ave and 32nd Ave NE
  • July 27, 2020: Sawing and Sealing will continue on 36th Ave NE and continuing on with streets in the area.

July 15, 2020

Work in the past week

  • July 13, 2020: Concrete removals on Tyler St NE started
  • July 14, 2020: Concrete canceled due to rain. Diamond grinding continued on Buchanan St NE and Lincoln St NE
  • July 15, 2020: Concrete poured on Tyler St NE Southbound between 35th Ave NE to 33nd Ave NE
  • July 16, 2020: Concrete removals on Polk St NE Southbound between 32nd Ave NE to 35th Ave NE
  • July 15, 2020: Concrete sawing and sealing from Arthur St NE  to Ulysses St NE from 33rd Ave NE through 29th Ave NE this will be on going for the next 2 weeks
  • July 16, 2020: Diamond grinding from Johnson St NE to Cleveland St NE on 32nd Ave NE also Johnson St NE to  Cleveland St NE
  • July 16, 2020: Concrete pour continues on Tyler St NE southbound and continuing to Polk St NE
  • July 17, 2020: concrete pour on Polk St NE and concrete removals on Tyler St. NE northbound side.

July 8, 2020

Diamond grinding was completed on 36th Ave from Polk St to Johnson St on Tuesday, July 7, 2020.

Diamond grinding started on Taylor St between 36th Ave and 35th Ave on Wednesday, July 8, 2020. Grinding will proceed to Fillmore St, Pierce St, Buchanan St and Lincoln St. between 36th Ave to 35th Ave.

Sawing will start 35th Ave and Tyler St on Thursday, July 9, 2020, and proceed to 32nd Ave on Monday, July 13, 2020. 

Removals will start at Tyler St from 35nd Ave to 32nd Ave on Tuesday, July 14, 2020. Concrete will be poured on Tyler St and 35th Ave on Monday, July 13, 2020. Once diamond grinding is complete on Lincoln St, grinding will start on 32nd Ave and 31st Ave between Johnson St and Cleveland St.

July 1, 2020

Diamond grinding started on Wednesday, July 1, 2020, starting on 36th Ave N between Polk St.NE and Johnson St NE. Once completed they will move to Lincoln St, Buchanan St, Pierce St, Fillmore St and Taylor St between 36th Ave N and 35th Ave NE.

Sawing will start on Thursday, July 2, 2020 on Polk St N between 36th Ave and 32nd Ave N.

Removals will start on Monday, July 13, 2020 on Polk St N between 36th Ave and 32nd Ave N.

Concrete pouring will start on Tuesday, July 14, 2020 on Polk St between 36th Ave and 32nd Ave N.

July 26, 2020

  • June 22, 2020 -  Milling partials on 36th Ave NE between Johnson St. and Polk St.
  • June 23, 2020 - June 24, 2020 - Jackhammering partials on 36th Ave NE between Johnson St. and Polk St.
  • June 25, 2020 - Pouring partials on 36th Ave NE between Johnson St and Polk St.
  • June 26, 2020 - General clean-up and restoration

June 29, 2020

Starting diamond grinding on 36th Ave N between Johnson St and Polk St and between 35th Ave NE and 36th Ave NE on the following streets:

  • Lincoln St
  • Buchanan St
  • Pierce St
  • Fillmore St
  • Taylor St

Following the above mentioned areas grinding will proceed on:

  • 31st Ave NE and 32nd Ave NE between Ulysses St and Johnson St.
  • 32nd Ave NE from Ulysses St to Garfield St
  • 31st Ave NE from Ulysses St to Hayes St NE

There will be no work on Friday, July 3, 2020.

June 17, 2020

We have completed the following work:

  • Continued to pour concrete on 36th Ave from Polk St to Johnson St northside

  • Poured concrete on 35th Ave and Tyler St. Replacing bituminous patch with concrete SW Quad
  • Other miscellaneous curb has been poured along with ped ramps on 36th Ave
  • Top soil restoration throughout project

On Thursday, June 18,  2020 we'll finish concrete pouring on 36th Ave, miscellaneous parking panels and ped ramps northside.

On Friday, June 19, 2020, we plan to do general project cleanup.

On Monday, June 22, 2020 we'll start milling particals depth on 36th Ave from Polk St. To Johnson St. and prep to pour on Tuesday, June 23, 2020.

June 9, 2020

Concrete was poured on 31st Ave and 32nd Ave between Johnson St and Ulysses St on the north side on June 9, 2020.

We started removals on June 8, 2020 on the south side of 36th Ave from Polk St to Johnson St NE, and completed on June 9, 2020.

We are pouring concrete on 36th Ave NE at Polk St and moving towards Johnson NE. W are finishing pouring concrete on the north side of 31st and 32nd between Ulysses and Johnson St.

We will be sawing on Friday, June 12, 2020 on 36th Ave NE on the north side

On Monday, June 15, 2020 we'll begin particles milling between Johnson St NE and Hayes St on 31st Ave NE, and between Johnson St NE and Garfield St NE on 32nd Ave NE.

June 3, 2020

We will be pouring concrete and placing topsoil at these locations:

  • 31st Ave southside and 32nd Ave southside between Johnson St and Ulysses St
  • Particals will be poured at Lincoln St to Taylor St
  • Between 35th Ave and 36th Ave

Concrete removal will start on Monday, June 8, 2020 at 32nd Ave and 31st Ave northside between Johnson St and Ulysses St, and on 36th Ave from Johnson St to Polk St. southside.

May 20, 2020

Removals started May 18, 2020 on 35th Ave and Lincoln up to 36th St then proceeded to 35th St and Buchanan St NE up to 36th St. The next street removed will be Pierce St in between 35th St and 36th St NE. Removals started on May 19, 2020 at 35th Ave and Fillmore St NE to 36th Ave NE, next 35th Ave and Taylor St NE. The same sequence for removals was used to pour back the streets and this was done May 20 and 21, 2020. This will be the second half of the streets.

Pedestrian ramps were removed at the following intersections:

  • 36th Ave NE and Filmore St NE SW
  • 36th Ave NE and Lincoln St NE SE
  • 36th Ave NE and Buchanan ST NE SE
  • 36th Ave NE and Pierce ST NE SE
  • 36th Ave NE and Taylor St NE SE

These will be poured back on May 20 and 21, 2020.

May 13, 2020

Concrete pouring started on May 11, 2020 on 35th Ave and Lincoln up to 36th St then proceeded to 35th St and Buchanan St NE up to 36th St. The next street poured will be Pierce St in between 35th St and 36th St NE. Only one half of the streets are being poured which is the left lane. Removal of the pedestrian ramps started on May 13, 2020 on Filmore St and 36th Ave opposite corners.

May 7, 2020

Construction is scheduled to begin on May 11, 2020, on Lincoln Ave and 35th St of the project area.

April 29, 2020

The contractor Ti-Zack is looking on completing saw cutting on Monday, May 4, 2020 and tentatively start removals on Wednesday, May 6, 2020 on Taylor St NE and 36th Ave NE.

April 20, 2020 Update

2019 Public Meetings

Neighborhood Construction Meeting
6:30 p.m., August 8 2019
Waite Park Recreation Center
1810 34th Ave NE
Minneapolis, MN

Formal Public Hearing
10 a.m., April 9, 2019
Council Chambers, City Hall
350 South 5th Street, 3rd Floor

Pre-Assessment Public Meeting
April 4, 2019

Public Open House
February 27, 2019

Contact

Joe Homan, WSB, Engineer; [email protected] or 612-209-6269

Tracy Lindgren, Engineer; [email protected] or 612-290-5898

Waite Park (2017-2018)

Waite Park Concrete Streets Rehab Overview Map

Project Status

CIP Status Stage 5: Completed

Project Details

Project Type:
Concrete Street Rehabilitation

Project Location:
Waite Park neighborhood

Construction Start Date:
Utility work in Spring 2018
Reconstruction work scheduled to start in May 2018.

Traffic Impact:
Short term detours

2018 Public Meetings:

Pre-Public Meeting
6:30 p.m., Wednesday, May 9, 2018
Waite Park Recreation Center
1810 34th Avenue Northeast

Formal Public Hearing
10 a.m., Tuesday, May 15, 2018
Council Chambers, City Hall
350 South 5th Street, 3rd Floor

2017 Public Meetings:

Pre-Public Meeting
6:30 p.m., Wednesday, February 22, 2017
Waite Park Recreation Center
1810 34th Avenue Northeast

Formal Public Hearing
9:30 a.m., Tuesday, February 28th, 2017
Council Chambers, City Hall
350 South 5th Street, 3rd Floor

Project Maps

2017 Waite Park Staging Areas Map

2017 Project Area Map

2018 Project Area Map (Task Order #3)

Waite Park Project Phases Map

Updates

November 2, 2018 Update

October 26, 2018 Update

October 19, 2018 Update

October 12, 2018 Update

October 5, 2018 Update

Contacts

Nicole Schmidt, Project Information Contact, [email protected] or 612-430-2805

Brad Fisher, Project Representative, [email protected] or 612-759-7240

Petru Vizoli, Engineer, [email protected] or 612-673-2368

Penn-Oliver (2017)

Penn Oliver Ave S Concrete Rehab Webmap.png

Project Status

CIP Status Stage 5: Completed

Project Details

Project Type

Concrete Street Rehabilitation

Project Location
Penn/Oliver Ave S from West Lake of the Isles PKWY to Douglas Ave

Construction Dates
Anticipated start – Week of June 18th, 2017
End – Week of August 13th, 2017

Traffic Impact
Short term detours

The purpose of the Concrete Streets Rehabilitation Program is to extend the life of some concrete city streets. This program is similar to the Asphalt Pavement Resurfacing Program with the objective to improve and maintain the roadway infrastructure. The goal is to target concrete streets that with proper concrete repair will extend the street’s life to improve ride quality and support neighborhood livability.

Concrete streets generally deteriorate over time as water and salt enter joints and cracks. Poor drainage, underlying soil condition, and higher traffic volumes can accelerate the deterioration. The repair of concrete primarily consists of saw cutting, removing and replacing concrete joints that have deteriorated and other pavement distresses. Other repair techniques include removal and replacement of concrete panels if it is determined the condition of the concrete does not warrant salvaging the panel pavement. Other improvements within the project limits include upgrades to select pedestrian ramps, replacement of select curb and gutter, and a diamond grind resurfacing of the street pavement.

Scope

The proposed project is part of the Concrete Streets Rehabilitation Program. Penn-Oliver Ave S was constructed in 1970 and is a good candidate for concrete repair and resurfacing. Concurrent with the street work, utility improvements will be completed associated with gas, and sewer.

For More Information

See this video for a deeper look into what concrete rehabilitation involves.

See this FAQ Sheet on concrete rehabilitation for more information.

Public Meetings

Pre-Public Hearing Meeting
6:30 p.m., Tuesday, May 9, 2017
Kenwood Community Center
2101 W Franklin Ave, Minneapolis, MN 55405

Public Hearing
9:45 a.m., Tuesday, May 16, 2017
Council Chambers, City Hall
350 South 5th street, 3rd Floor

Project Contacts

Nicole Schmidt, Project Information Contact, [email protected] or 612-430-2805

Brad Fisher, Project Representative, [email protected] or 612-759-7240

Elisha Langat, Engineer, [email protected] or 612-673-5974

Penn-Oliver Email Updates
To sign up for updates or to access your subscriber preferences, please enter your contact information below.

Contact

Tracy Lindgren, Construction Engineer; [email protected] or 612-290-5898

 

Last updated Oct 16, 2020

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-263-6850.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

Public Works  ©1997-2020 City of Minneapolis, MN

CONNECT

311 call center

311 TTY relay service

City of Minneapolis Facebook City of Minneapolis Twitter City of Minneapolis YouTube ChaNNEL Minneapolis 311 Watch Minneapolis City Council TV City of Minneapolis LinkedIn

Minneapolis, City of Lakes logo