18th Ave NE Reconstruction (Johnson St NE to Stinson Blvd)

In 2020, the City of Minneapolis will be reconstructing 18th Ave NE in northeast Minneapolis between Johnson St NE and Stinson Blvd.

18th Ave NE Johnson to Stinson Webmap 11-5-18

Project status

Project Status: Construction

Project details

Description

The City of Minneapolis is planning to reconstruct approximately 0.5 miles of 18th Avenue NE in the Northeast Park and Windom Park neighborhoods. The project will replace aging pavement and improve the right-of-way for all users and modes of travel. This project provides an opportunity to incorporate ADA compliant pedestrian ramps, address sidewalk obstructions and sidewalk/trail gaps, and add boulevard space with street trees. The project will connect into the recently constructed trail to west along 18th Ave NE.

See the recommended design for the 18th Ave NE project.

Project Type

The project includes full reconstruction of the entire right-of-way and will include filling sidewalk gaps, ADA pedestrian ramps, boulevard space, pavement, curb and gutter, and utility improvements. The project will also include new signage, new pavement markings, and improve non-motorized crossings to Northeast Minneapolis’ major retail center.

Project Limits

Approximately 0.5 miles of 18th Avenue NE between Johnson Street NE and Stinson Parkway.

Project Timeline

18th Ave NE Street Reconstruction Timeline Graphic

Utility Construction on 18th Ave NE will begin Monday, March 30 and run through late May 2020.

CenterPoint Energy’s project is anticipated to last two months. Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, will replace natural gas mains and connect natural gas service lines to the new mains.

18th Ave NE street reconstruction work is expected to start in mid-to late May as CenterPoint finishes their utility work.

Traffic Impacts

On 18th Avenue NE, crews from Michels Corporation will begin at Stinson Parkway working west. Each block will be closed for approximately one to two weeks. Eastbound traffic will be detoured. CenterPoint will notify residents or business owners if the crews need to cross any driveways.

During construction, residents, businesses, and visitors may expect traffic detours, noise, vibration, and dust in work areas. In addition, temporary impacts such as lane restrictions, intersection reductions, parking restrictions or revised pedestrian and bicycle routes may be expected during construction. Property access will be maintained throughout construction. Specific construction staging and traffic detour information will be posted here as the project gets closer to construction.

Project Meetings

Weekly Stakeholder Meeting Reminder

Virtual weekly project stakeholder meetings will be held every Thursday using Microsoft Teams. Please use the link below to join the meeting.

Join the Virtual Weekly Stakeholders Meeting

Every Thursday, 11:00 - 11:30 a.m.

These meetings help us to give you more detailed information about work progress on a weekly basis and to have discussion on any concerns or questions you have about the project. Please send me (Ayalew) an email or give me a call if you have difficulty using the link above.

If no one joins the meeting within 15 minutes the meeting will end, but you can still contact me via phone or email.

Ayalew Getaneh, Construction Engineer; 612-673-6055 or [email protected]

Documents

Project Fact Sheet

Recommended Layout - May 2019

18th Ave NE Virtual Construction Kick-off Meeting Presentation - May 13, 2020

Project updates

October 20, 2020 Update

Major Activities over the Past Week

The following major activities have been carried out in all phases over the past week:

  • Johnson intersection to Ulysses:
    • At  the intersection of Johnson
      • The final pavement layer is installed.
      • Mill and overlay to match the existing pavement on Johnson St.
      • Sod installed at the SE corner boulevard.
    • Between Johnson and Ulysses
      • The final pavement layer is installed.
      • The pavement transverse Joint (Saw and Seal) conducted.
      • Sod installed.
      • The shared use trail preparation completed and it's ready to be paved.
  • Ulysses to Arthur
    • The final pavement layer is installed.
    • The pavement transverse Joint (Saw and Seal) conducted.
    • Sod installed.
    • The section of the shared use trail preparation completed and ready to be paved.
    • Miscellaneous concrete work.
  • Arthur to Stinson Blvd
    • The final pavement layer is installed.
    • The pavement transverse Joint (Saw and Seal) conducted.
    • Sod installed.
    • Miscellaneous concrete work.

Coming Up

  • All Phases (Johnson intersection to Stinson Blvd )
    • Pavement striping and signs will be installed.
  • Johnson  to Hayes St
    • The shared-use trail will be paved.

Traffic Impacts & Access

  • The Post Office access 
    • The post office west driveway is accessible through Johnson intersection
  • The dead-end alley between Arthur and Cleveland
    • The alley is accessible through Cleveland St.
  • The Stinson Market Place
    • The Stinson Market place is accessible through Stinson Blvd Intersection.  
  • Between the Post office west driveway and Stinson Market Place west driveway
    • This section will remain closed till pavement striping and traffic signs installed. However, it's accessible for local traffic.

Progress Photos

18th Ave NE Construction Photo 10-20-20_1

The final asphalt layer installation at Johnson intersection

18th Ave NE Construction Photo 10-20-20_4

Ready for sodding

18th Ave NE Construction Photo 10-20-20_5

After Sod installed / the current view of 18th between Hayes and Stinson

October 13, 2020 Update

Major Activities over the Past Week

Over the past week the following major activities performed at all phases:

  • Johnson intersection
    • NW Corner: 
      • Sidewalk and pedestrian ramp installed.
      • 2nd and 3rd lift pavement layers installed.
      • Utility manholes raised to the final road elevation.
    • SE Corner:
      • Sidewalk and pedestrian ramp installed.
      • Boulevard preparation work performed.
  • Between Johnson and Ulysses
    • Raising irons/utility manholes to the final road elevation completed.
    • Grading and preparation work for the shared use trail between the post office driveways completed.
  • Ulysses to Arthur
    • Raising irons/utility manholes to the final road elevation completed.
    • Preparation work to connect the new shared bike trail with the existing on progress.
  • Between Arthur and Stinson Market place
    • Raising irons/utility manholes to the final road elevation completed.
    • Concrete special walks installed to connect the bike trail and the sidewalk.
    • The utility companies ( Xcel, Comcast, Us internet and CenturyLink) apparatus  relocated to the new installed poles.
  • Between Stinson Market Place west entrance and New Brighton Blvd
    • 2nd and 3rd lift of asphalt pavement layers installed, and it's ready for the final lift to be installed.

Coming Up

  • Johnson intersection to Ulysses:
    • At Johnson intersection
      • The final wear/ pavement layer will be installed.  .
      • Milling and overlay to match the existing pavement on Johnson St will be conducted.
    • Between Johnson and Ulysses
      • The final wear / pavement layer will be installed.
      • Installing sod will begin.
  • Ulysses to Arthur
    • Preparation work to connect the new shared bike trail with the existing will continue.
    • Sod will be installed.
  • Arthur to Stinson Market place driveway:
    • The final wear/ pavement layer will be installed.
    • Installing sod will begin.
    • Miscellaneous concert work.
  • Between Stinson Market Place west entrance and Stinson Intersection :
    • The final wear/ pavement layer will be installed on Tuesday 10/13, weather permitting .
    • Miscellaneous concert work between NE Stinson Blvd and New Brighton Blvd.

Traffic Impacts & Access

  • Johnson intersection  
    • It is planned to pave the  final pavement layer on Tuesday 10/13, weather permitting. Johnson intersection will be widely open for traffic after the final layer paved.
    • 18th east bound traffic towards Johnson intersection and west bound from Johnson St will be opened for traffic on Wednesday 10/14.
  • The Post Office access 
    • Weather permitting, we planned to pave the final layer of asphalt pavement on Tuesday 10/13. Once the pavement completed, the post office will be accessible through Johnson intersection, and the west entrance driveway will be opened.
  • The dead-end alley between Arthur and Cleveland
    • The alley remains open and accessible through Cleveland St. However, there might be a temporary blocking during paving in front of the alley on Tuesday 10/13.
  • The Stinson Market Place
    • The final pavement lift is planned to pave on Tuesday 10/13, weather permitting.
    • Once the final pavement completed, The Stinson Market place will be accessible through Stinson Intersection starting on Wednesday 10/14. Till then, please use the designated detour. 
  • 18th between the Post office west driveway and Stinson Market Place west driveway
    • This section will remain closed except for local traffic.

Progress Photos

18th Ave NE Construction Photo 10-8-20_1

The upgraded new pedestrian ramp and sidewalk at the NW corner of Johnson St and 18th Ave NE

18th Ave NE Construction Photo 10-8-20_2

The new shared bike trail in front of the post office is ready be paved.

18th Ave NE Construction Photo 10-8-20_5

Utility manholes/irons raised to the final road level

October 5, 2020 Update

Major Activities over the Past Week

Over the past week the following project major activities were performed at all phases:

  • Johnson intersection
    • NW Corner : 
      • Curb & gutter and a pedestrian ramp installed.
    • SE Corner:
      • Curb & gutter and a pedestrian ramp installed.
      • signal and street light foundations installed.
  • Between Johnson and Ulysses
    • The post office west driveway installed.
    • A shared use trail preparation work between the post office driveways.
    • Detour signs posted to direct pedestrian access on the north side of 18th.
  • Ulysses to Arthur
    • raising irons (utility manholes) on progress.
    • concrete special walks installed to connect the bike trail and the sidewalk.
    • Xcel Energy relocate power poles.
  • Between Arthur and Stinson Market place
    • raising irons (utility manholes) on progress.
    • concrete special walks installed to connect the bike trail and the sidewalk.
    • Xcel Energy relocate power poles.
  • Between Stinson Market Place west entrance and New Brighton Blvd
    • Bus pads installed.
    • Concrete island/median installed by the Stinson pkwy.
    • Pedestrian crossing ramps installed.
    • New median and ped crossing ramps installed to connect New Brighton Blvd and 18th Ave NE on the north side of 18th.

Coming Up

  • Johnson intersection to Ulysses:
    • At Johnson intersection
      • At NW corner: sidewalk, pavement restoration (2nd and 3rd lift asphalt), raising irons ( utility manholes); and weather permitting, the final lift of asphalt will be installed by the end of the week or early next week. 
      • SE corner: sidewalk will be installed to connect with the existing, and pavement restoration will be conducted.
    • Between Johnson and Ulysses
      • raising irons ( utility manholes).
      • Preparation work for the new shared bike trail will continue.
  • Arthur to Stinson Market place driveway:
    • raising irons (utility manholes) will continue.
  • Between Stinson Market Place west entrance and Stinson Intersection :
    • 2nd and 3rd lifts of asphalt pavement will be installed.

Traffic Impacts & Access

  • The Post Office access: 
    • The access remain the same as it was last week. It's accessible through 19th Ave NE and Hayes St NE. Detour signs posted showing " Post Office Access Only". 
  • Johnson intersection:  
    • Johnson St NB and SB traffic flow will remain as it was last week till the intersection final pavement wear installed.
    • 18th east bound traffic towards Johnson will remain close till the intersection work completed. Please use all other alternate routes or the follow the detour signs towards 19th Ave NE. 
  • The dead-end alley between Arthur and Cleveland St: 
    • The alley remains open and accessible through Cleveland St.
  • The Stinson Market Place:
    • It's accessible through the newly installed driveway on the west. "Stinson Market Place" detour signs posted to indicate the access. 
      • From Stinson Blvd: through 19th Ave NE west bound – left turn on Benjamin St NE – another left turn on 18th Ave NE.
      • For Johnson St: through east bound on 19th Ave NE – right turn on Benjamin St NE – left turn on 18th Ave NE.
    • Note: For Stinson Market place truck deliveries, Johnson intersection is accessible. Please contact us for the scheduled delivery to get the access. Please do not use residential streets for the bigger trucks deliveries.

Progress Photos

 18th Ave NE Construction Photo 10-5-20_1

The Post office West driveway

18th Ave NE Construction Photo 10-5-20_2

New curb & gutter on Johnson St south of 18th St

18th Ave NE Construction Photo 10-5-20_3

Xcel Energy relocating power poles that conflict with the new sidewalks and ped ramps.

September 28, 2020 Update

Major Activities over the Past Week

Over the past week the following project major activities performed at all phases:

  • Johnson intersection: To avoid traffic closure, the activities at the intersection undergoing section by section. 
    • NW Corner : 
      • A pavement section removed.
      • storm sewer system upgraded ( a new catch basin and a connection pipe).
      • base lift asphalt installed.
    • SE Corner:
      • Pavement section removed.
      • Signal base installed.
      • Base lift asphalt installed.
  • Between Johnson and Ulysses
    • The post office west driveway removed.
    • The south side of 18th sidewalk removed. Pedestrians are using the sidewalk on the north side of 18th as a detour.
  • Ulysses to Arthur
    • Preparation of tree pits on progress.
  • Between Arthur and Stinson Market place
    • Preparation of tree pits on progress.
  • Between Stinson Market Place west entrance and Stinson Intersection 
    • The Stinson Market Place east driveway installed.
    • curb and gutter installed on both sides.
    • Sidewalk installed on the north side of 18th.
    • Installation of signal connection conduit and handholds on progress.

Coming Up

  • Johnson intersection to Ulysses:
    • At Johnson intersection
      • At NW corner: Curb & gutter and pedestrians ramp will be installed.
      • SE side: Curb & gutter,  pedestrians ramp and sidewalk will be installed.
      • Next week it is planned to pave and restore the intersection, weather permitting
    • Between Johnson and Ulysses
      • The post office west driveway will get reinstalled.
      • Preparation work for the new shared bike trail will continue.
  • Arthur to Stinson Market place driveway:
    • Xcel Energy planned to relocate  power poles out of the new sidewalk area.
    • Tree pits preparation will continue.
  • Between Stinson Market Place west entrance and Stinson Intersection :
    • Bus pads ( east and westbound) will install
    • Concrete island/median will install by Stinson intersection.
    • Signal system interconnect conduit installation will continue.

Traffic Impacts

  • The Post Office access: 
    • The access remain the same as it was last week. It's accessible through 19th Ave NE and Hayes St NE. Detour signs posted showing " Post Office Access Only". 
  • Johnson intersection:
    • Johnson St NB and SB traffic flow will shift more towards the east side due to the NW corner work.
    • 18th east bound traffic towards Johnson will remain close till the intersection work completed. Please use all other alternate routes or the follow the detour signs towards 19th Ave NE. 
  • The dead-end alley between Arthur and Cleveland St: 
    • The alley remains open and accessible through Cleveland St.
  • The Stinson Market Place:
    • It's accessible through the newly installed driveway on the west. "Stinson Market Place" detour signs posted to indicate this access. 
      • From Stinson Blvd: through 19th Ave NE west bound – left turn on Benjamin St NE – another left turn on 18th Ave NE.
      • For Johnson St: through east bound on 19th Ave NE – right turn on Benjamin St NE – left turn on 18th Ave NE.
    • Note: For Stinson Market place truck deliveries, Johnson intersection is accessible. Please contact us for the scheduled delivery to get the access. Please do not use residential streets for the bigger trucks deliveries. 

Progress Photos

18th Ave NE Construction Photo 9-28-20_1

Stinson Market Place east driveway

18th Ave NE Construction Photo 9-28-20_2

Curb and gutter between Stinson Market place west driveway and Stinson intersection

18th Ave NE Construction Photo 9-28-20_3

A section of base lift asphalt installed at the NW corner of Johnson intersection

September 21, 2020 Update

Major Activities over the Past Week

Over the past week, the following project major activities were performed at phases 1, 3, and 4:

  • Johnson intersection to Ulysses
    • The 2nd and 3rd asphalt pavement lifts installed.
    • Sidewalk on the north side of 18th and at the NE corner of Johnson and 18th intersection installed.
    • Driveway and alley aprons installed.
  • Between Arthur St and Stinson Market place
    • Sidewalk and pedestrian ramps installed.
  • Between Stinson Market Place west entrance and Stinson Intersection 
    • The 1st lift of asphalt installed.

Coming Up

  • Johnson intersection to Ulysses:
    • At Johnson intersection
      • At NW corner pavement and ped ramp removal.
      • A catch basin and a connection pipe at the NW corner.
      • Curb & gutter and ped ramp at the NW corner.
      • Weather permitting, pavement restoration work will be done.
    • Between Johnson and Ulysses
      • The post office west driveway will get removed and reinstalled.
      • The sidewalk on the south side of 18th will get removed, and preparation work for the new shared bike trail will be done.
  • Arthur to Stinson Market place driveway:
    • Bike trail and sidewalk connection ramp will get installed.
  • Between Stinson Market Place west entrance and Stinson Intersection :
    • Curb and gutter, sidewalk and driveway apron will be installed.

Traffic Impacts

  • The Post Office access: 
    • The access remain the same as it was last week. It's accessible through 19th Ave NE and Hayes St NE. Detour signs posted showing " Post Office Access Only". 
  • Johnson intersection:  
    • Johnson St NB and SB traffic flow will shift more towards the east side due to the NW corner work.
    • 18th east bound traffic towards Johnson will remain close till the intersection work completed. Please use all other alternate routes or the follow the detour signs towards 19th Ave NE. 
  • The dead-end alley between Arthur and Cleveland St: 
    • The alley remains open and accessible through Cleveland St.
  • The Stinson Market Place:
    • It's accessible through the newly installed driveway on the west. "Stinson Market Place" detour signs posted to indicate this access. 
      • From Stinson Blvd: through 19th Ave NE west bound – left turn on Benjamin St NE – another left turn on 18th Ave NE.
      • For Johnson St: through east bound on 19th Ave NE – right turn on Benjamin St NE – left turn on 18th Ave NE.
    • Note: For Stinson Market place truck deliveries, Johnson intersection is accessible. Please contact us for the scheduled delivery to get the access. Please do not use residential streets for big truck deliveries. 

Progress Photos

18th Ave NE Construction Photo 9-21-20_1

2nd and 3rd lifts of asphalt pavement installation at Johnson intersection

18th Ave NE Construction Photo 9-21-20_2

Curb and gutter at NE corner of Johnson and 18th

18th Ave NE Construction Photo 9-21-20_3

1st lift asphalt installed between Stinson Market place and Stinson intersection

18th Ave NE Construction Photo 9-21-20_4

The current view of 18th between Arthur and Stinson

September 14, 2020 Update

Major Activities over the Past Week

Over the past week the following project major activities performed at phase 1,2,3 and 4:

  • Johnson intersection-to-Ulysses
    • 1st lift asphalt pavement installed.
    • sidewalk preparation work performed.
  • Ulysses St. to Arthur St.
    • Grading and preparation work in the boulevard area.
  • Arthur St. to Stinson Market place
    • The 2nd and 3rd lifts of asphalt pavement completed.
    • Boulevard top soil installed.
  • Stinson Intersection 
    • The last portion of the project concrete pavement removal by Stinson intersection completed.
    • Subgrade correction and preparation work started.

Coming Up

  • Johnson intersection to Ulysses:
    • curb & gutter
    • Sidewalk on the north side of 18th will be installed.
    • Weather permitting, the 2nd and 3rd lifts of asphalt will be placed by the end of this week or early next week.
  • Ulysses to Arthur:
    • Tree pits preparation and boulevard top soil.
  • Arthur to Stinson Market place driveway:
    • Tree pits preparation.
  • Stinson intersection:
    • Final grading preparation work and aggregate base.
    • Weather permitting, the 1st lift of asphalt pavement by the end of the week or early next week.

Traffic Impacts

  • The Post Office access: 
    • The access remain the same as it was last week. It's accessible through 19th Ave NE and Hayes St NE. Detour signs posted showing " Post Office Access Only". 
  • Johnson intersection:
    • Johnson St NB and SB traffic flow will remain in the middle and outer lane on the west until the layers of asphalt lifts between Ulysses and Johnson placed.
    • 18th Ave NE east bound and west bound at Johnson intersection remain closed.
    • 18th east bound traffic towards Johnson, use all other alternate routes or the detour through 19th Ave NE.
    • Traffic Control Agent assigned at this intersection to facilitate a smooth traffic flow during the rush hours.
  • The dead-end alley between Arthur and Cleveland St: 
    • The alley is accessible through Cleveland St.
  •  The Stinson Market Place:
    • It's accessible through the newly installed driveway on the west. Detour signs posted to indicate this access. 
    • From Stinson Blvd: through 19th Ave NE west bound – left turn on Benjamin St NE – another left turn on 18th Ave NE.
    • For Johnson St: through east bound on 19th Ave NE – right turn on Benjamin St NE – left turn on 18th Ave NE.

Progress Photos

18th Ave NE Construction Photo 9-14-20_1

The current view between Arthur and Stinson Market Place west driveway

18th Ave NE Construction Photo 9-14-20_2

Pavement removal by Stinson Market Place drvieway and Stinson Blvd

18th Ave NE Construction Photo 9-14-20_3

Subgrade preparation between Stinson Market Place west driveway and Stinson Blvd.

September 7, 2020 Update

Major Activities Over the Past Week

Over the past week the following project major activities performed at phases 1, 2 and 3 locations:
  • Johnson intersection - Phase 2
    • Subgrade preparation work between Ulysses and Johnson St completed and ready for asphalt pavement
  • Between Ulysses and Arthur - Phase 1
    • Grading and preparation work in the boulevard and sidewalk areas performed
  • Between Arthur and Stinson - Phase 3
    • Topsoil installation on progress
    • Sidewalk area grading and preparation work performed

Coming Up 

  • Phase 1:
    • Behind the curb preparation work will continue
    • Sidewalk will be installed
  • Phase 2:
    • 1st lift of asphalt between Ulysses and Johnson will be installed
    • curb, gutter and sidewalk on the north side of 18th will be installed
  • Phase 3:
    • The 2nd and 3rd lifts of asphalt pavements will be installed on Tuesday, weather permitting
  • Phase 4:
    • Pavement removal work will begin from the west driveway of the Stinson Market place to NE Stinson Blvd. intersection 

Traffic Impacts

  • The Post Office access:
    • The access remain the same as it was last week. It's accessible through 19th Ave NE and Hayes St NE. Detour signs posted showing " Post Office Access Only".
    • The post office east driveway widen and temporary ramped to accommodate the delivery trucks.
  • Johnson intersection:
    • Johnson St NB and SB traffic flow will remain in the middle and outer lane on the west until the roadway between Ulysses and Johnson is paved.
    • 18th Ave NE east bound and west bound at Johnson intersection remain closed.
    • 18th east bound traffic towards Johnson, use all other alternate routes or the detour through 19th Ave NE.
    • Traffic Control Agent assigned at this intersection to facilitate a smooth traffic flow during the rush hours.
  • The dead-end alley between Arthur and Cleveland St:
    • As it's indicated on the information letter, the second and third lifts of asphalt pavement will be installed on Tuesday, September 8, 2020 weather permitting. During the asphalt paving, the dead-end alley access will be completely closed off while paving occurring and a few hours after the asphalt has been placed. The alley will be accessible by the end of the same day or the next day morning.
  • The Stinson Market Place:
    • As indicated in the notice letter that we distributed, the final segment of the project (from the Stinson Market west driveway-to-Stinson Blvd NE ) will begin on Wednesday Sept 9, 2020. Due to this the market place east driveway will be closed.
    • Access: The newly installed driveway on the west will be open and accessible. Detour signs to indicate the access to the Market Place will be posted. The detour will be through west bound 19th Ave NE – left turn on Benjamin St NE-- and another left turn on 18th Ave NE. For the east bound on 19th Ave NE, we will also post an additional sign at 19th and Benjamin intersection.  

Progress Photos 

 Image - The section between Ulysses and Johnson intersection is ready for asphalt pavement

The section between Ulysses and Johnson intersection is ready for asphalt pavement.

 Boulevard preparation on progress - phase 3 - 18th AVE NE

Arthur to Stinson marketplace - the southside boulevard preparation completed and top soil installed.

 Arthur to Stinson marketplace

 Boulevard preparation on progress - phase 3 

August 31, 2020 Update

Major Activities Over the Past Week

 

Over the past week the following project major activities performed at phases 1, 2 and 3 locations:
  • Johnson intersection - Phase 2
    • The storm sewer system installed and completed between Ulysses and east of Johnson St.
  • Between Ulysses and Arthur - Phase 1
    • Grading and preparation work in the boulevard and sidewalk areas performed.
  • Between Arthur and Stinson - Phase 3
    • Curb and gutter installed and completed.
    • Bus pads installed at the designated locations.
    • All driveway aprons installed including the dead end alley

Coming Up

  • Phase 1:
    • Preparation work behind the curb (in the boulevard area) will continue.
    • Sidewalk will be installed.
  • Phase 2 ( at Johnson intersection)
    • Grading and preparation work between Ulysses and Johnson.
    • Layers of asphalt pavement will be installed, weather permitting.
  • Phase 3:
    • Layers of asphalt pavements will be installed, weather permitting.

Traffic Impacts

  • Johnson intersection:  
    • o Johnson St NB and SB traffic flow will remain in the middle and outer lane on the west until the roadway paved between Ulysses and Johnson St.
    • 18th Ave NE east bound and west bound at Johnson intersection remain closed.
    • 18th east bound traffic towards Johnson, use alternate routes or the detour through 19th Ave NE towards Johnson St.
    • Traffic Control Agent assigned at this intersection to facilitate a smooth traffic flow during the rush hours.
       
  • Post Office access:
    • Accessible through 19th Ave NE and Hayes St NE. A detour sign set up showing " Post Office Access Only". This will remain for the next 2 -3 weeks.
    • The post office east driveway widen and ramped temporary to accommodate the delivery trucks. 
  • The dead-end alley between Arthur and Cleveland St: 
    • The alley driveway and apron installation completed. Once the installed concrete cured, we planned to have the 2nd and 3rd asphalt pavement lifts by the end of this week, weather permitting.
    • The access will remain closed this week until asphalt pavement installed. We will communicate you if there is a plan change.
  • The business center by the Stinson:
    • The traffic impact on this section has no change from last week. It is accessible through Stinson Blvd using the east driveway. The west driveway will remain closed till the new curb & gutter and asphalt pavement installed. Once we done these, we'll switch the access to the west entrance in order to finish up the remaining stretch up to Stinson intersection. This is just a heads up. We will notify/inform you the exact date a week before the traffic switch happen.

Progress Photos

 The dead-end alley driveway apron

Bus pad near Arthur intersection.

 The dead-end alley driveway apron

 

The dead-end alley driveway apron

 Installation of storm sewer system near Johnson intersection on the east

 Installation of storm sewer system near Johnson intersection on the east

 The west side driveway apron installed by the business center near Stinson Blvd intersection

The west side driveway apron installed by the business center near Stinson Blvd intersection

August 24, 2020 Update

Major Activities Over the Past Week

the following project major activities performed at Phase 1 and 3 locations:

  • Between Ulysses and Arthur (Phase 1)

    • The 2nd and 3rd lifts of asphalt pavement completed
    • The post office temporary access ramp and detour signs installed through Hayes St.
  • Johnson intersection (Phase 2)

    • Traffic control set up completed to accommodate the intersection construction activities. This set up leaves one lane traffic in each northbound and southbound directions
    • The middle two lanes pavement removal and reconstruct sanitary sewer manhole performed.
    • Grading, compacting and asphalt paving performed for the two middle lanes of the intersection.
    • Traffic redirected on to the newly paved middle two lanes, and the outer lane pavement removal continued adjacent to 18th on the east.
  • Between Arthur and Stinson (Phase 3)

    • The first lift of asphalt pavement completed.
    • Curb and gutter installed on both sides of 18th .

Coming Up

  • Phase 1:

    • Preparation work behind the curb (the boulevard area).
  • Phase 2 ( at Johnson intersection)

    • Storm sewer work between Ulysses and Johnson intersection.
    • backfill and grading work between Ulysses and Johnson
    • Layers of asphalt pavement will be installed, weather permitting.
  • Phase 3:

    • Sidewalk and driveways will be installed.

Traffic Impacts

  • Johnson intersection:  

    • Johnson NB and SB traffic redirected in to the two middle lanes, and will remain open.
    • 18th Ave NE east bound and west bound at Johnson intersection remain closed. A detour signs set up through 19th Ave NE towards Johnson St.
    • We'll be working on the outer lanes of Johnson St. Please expect traffic delays due to these activities and the restricted lane width.
  • Post Office access:

    • It's accessible through 19th Ave NE and Hayes St NE. A detour sign set up showing " Post Office Access Only". This will remain for the next 2 -3 weeks.
    • The post office east driveway widen and ramped temporary to accommodate the delivery trucks. 
  • The dead-end alley between Arthur and Cleveland St: 

    • We have sent a notification letter to inform the residents who access their properties through the alley.  As we mentioned in the letter, the alley driveway apron will be installed in this week. Due to this the alley will not be accessible at least for the next 7 days till the concrete cure or ready to drive on it. 
  • The business center by the Stinson:

    • The traffic impact on this section has no change from last week. It is accessible through Stinson Blvd using the east driveway. The west driveway will remain closed till the new curb & gutter and asphalt pavement installed. Once we done these, we'll switch the access to the west entrance in order to finish up the remaining stretch up to Stinson intersection. This is just a heads up. We will notify/inform you the exact date a week before the traffic switch happen.

Progress Photos

 The 1st lift insatlled between Arthur and Stinson - Phase 3

The 2nd and 3rd lift pavement installed between Ulysses and Arthur - Phase 1

 Curb and gutter installed between Arthur and Stinson - Phase 3

Curb and gutter installed between Arthur and Stinson - Phase 3

 Pavment removal at two middle lanes of Johnson intersection

Pavement removal at two middle lanes of Johnson intersection

August 17, 2020 Update

Major Activities over the Past Week

Over the past week the following project major activities performed at Phase 1 and 3 locations:

  • Between Ulysses and Arthur - (Phase 1)

    • The last week plan to install the 2nd and 3rd lifts of asphalt pavement postponed to this week due to the last week rain.
  • Between Arthur and Stinson - (Phase 3)

    • The road base (subgrade) preparation and soil correction work performed.
    • Class V material installed.
    • Fine grading is performed, and the section is ready for the 1st lift of asphalt pavement and curb & gutter.

Coming Up

  • Phase 1:

    • The 2nd and 3rd lifts of asphalt pavement will be placed.
  • Phase 2 ( at Johnson intersection)

    • Johnson intersection pavement removal work ( the middle two lanes)
    • Re-construct a drainage structure ( manhole) at the middle of the intersection.
  • Phase 3:

    • The 1st lift of asphalt pavement will be installed.
    • Curb and gutter will be installed, weather permitting

Traffic Impacts

  • Johnson intersection:  As we mentioned last week, the work at Johnson intersection will start as of today. Johnson NB and SB ( the outer lanes) in each direction will remain open for the traffic. We'll be working in the middle two lanes. Please expect traffic delays due to these activities.

  • Post Office access: It's still accessible through Johnson St north bound. However, when we move into the Johnson intersection outside lanes work, the access will be switched through Hayes St .

  • The dead-end alley between Arthur and Cleveland St: Depending on the amount of work in front of the alley entrance, the alley access might be switched between Arthur and Cleveland.

  • The business center by the Stinson is accessible through Stinson Blvd using the east driveway. The west driveway will remain closed till the new curb & gutter and asphalt pavement installed. Once we done these, we'll switch the access to the west entrance in order to finish up the remaining stretch up to Stinson intersection. This is just a heads up. We will notify/inform you the exact date a week before the traffic switch happen.

  • Other than the above considerations, 18th Ave between Ulysses and Stinson will remain closed except for local traffic.

Progress Photos

18th Ave NE Construction Photo 8-17-20_1

Subgrade prep (Phase 3)

18th Ave NE Construction Photo 8-17-20_2

Soil correction and prep work (Phase 3)

18th Ave NE Construction Photo 8-17-20_3

Class V material installed and fine grading (Phase 3)

18th Ave NE Construction Photo 8-17-20_4

 

The section from Arthur to Stinson business area entrance is ready for the 1st asphalt lift

August 10, 2020 Update

Major Activities over the Past Week

Over the past week the following project major activities were completed at Phase 1 and 3 locations:

  • Between Ulysses and Arthur (Phase1)

    • Bus pads installed.
    • Sidewalk and pedestrian crossing ramps installation continued.
  • Between Arthur and Stinson (Phase 3)

    • The road base (subgrade) preparation and soil correction work performed.
    • Placing class v material started.
    • Plug and fill of abandoned in place storm sewer line conducted .

Coming Up

  • Phase 1:

    • The next 2 lifts of asphalt pavement will be placed, weather permitting.
    • Restoration work behind the curb will continue.
  • Phase 3:

    • The road base (subgrade) preparation and soil correction work will continue.
    • The final grading will be done and the phase will be ready for the 1st lift of asphalt pavement, weather permitting.
    • The lighting and traffic signal connection conduit and handholds will be installed.

Traffic Impacts

Traffic impacts will remain the same as the last week.

  • The work on Johnson intersection will start on the week of August 18th. Till then the Post Office is still accessible through Johnson St. However, when we move into the Johnson intersection work, the access will be switched through Hayes St and the driveway on the east. We planned Ulysses to be a detour for the post office access. However, there are some remaining work at the at this intersection and decided to use Hayes as the access detour.

  • The dead end alley between Arthur and Cleveland St: The alley access switched back through Arthur. However, depending on the amount of work in front of the alley entrance, the alley access might be switched to Cleveland again.

  • The business center by the Stinson is accessible through Stinson Blvd using the east driveway. The west driveway will remain closed till the new curb & gutter and asphalt pavement installed. Once we done these, we'll switch the access to the west entrance in order to finish up the remaining stretch up to Stinson intersection. This is just a heads up. We will notify/inform you the exact date a week before the traffic switch happen.

  • Other than the above considerations, 18th Ave between Ulysses and Stinson will remain closed except for local traffic.

Progress Photos

18th Ave NE Construction Photos 8-10-20_1

Bus pad installed at Hayes intersection - Phase 1

18th Ave NE Construction Photos 8-10-20_2

Soil correction - Phase 3

18th Ave NE Construction Photos 8-10-20_3

Placing class v material after the soil correction is done

18th Ave NE Construction Photos 8-10-20_4

July 31, 2020 Update

Major Activities over the Past Week

Over the past week the following project major activities performed at Phase 1 and 3 locations:

  • Between Ulysses and Arthur (Phase 1)

    • The alleyways driveway approaches installed and completed.
    • The post office east driveway approach installed. When the concrete cured, the gap behind the driveway will be patched with asphalt.
    • Concrete pavement restoration on Hayes St stretch completed.
    • Sidewalk and pedestrian crossing ramps installation started.
  • Between Arthur and Stinson (Phase 3)

    • The existing (old) storm sewer main line removal completed.
    • The new storm sewer lateral connections and curb inlets installation completed.
    • Sanitary manhole re-construct completed.

Coming Up

  • Phase 1

    • Sidewalk and pedestrian crossing ramps installation will continue.
    • Bus pad will install.
    • Restoration work behind the curb.
  • Phase 3

    • The road base (subgrade) preparation and soil correction work.

Traffic Impacts

  • The traffic impacts will remain the same as the last week.

    • The Post Office is still accessible through Johnson St. However, when we move into the Johnson intersection work, the access will be switched through Ulysses St and the driveway on the east.
    • The dead end alley between Arthur and Cleveland St: The alley access switched back through Arthur. However, depending on the amount of work in front of the alley entrance, the alley access might be switched to Cleveland again.
    • The business center by the Stinson is accessible through Stinson Blvd using the east driveway. The west driveway will remain closed till the new curb & gutter and asphalt pavement installed. Once we done these, we'll switch the access to the west entrance in order to finish up the remaining stretch up to Stinson intersection. This is just a heads up. We will notify/inform you the exact date a week before the traffic switch happen.
    • Other than the above considerations, 18th Ave between Ulysses and Stinson will remain closed except for local traffic.

Progress Photos

18th Ave NE Construction Photo 7-31-20_1

The Post Office east driveway installed (Phase 1)

18th Ave NE Construction Photo 7-31-20_2

Concrete pavement restoration on Hayes St after the sanitary mainline replacement (Phase 1)

18th Ave NE Construction Photo 7-31-20_3

Sidewalk and pedestrian crossing ramp (Phase 1)

18th Ave NE Construction Photo 7-31-20_4

Sanitary manhole section removal (Phase 3)

18th Ave NE Construction Photo 7-31-20_5

Sanitary manhole reconstruction (Phase 3)

July 24, 2020 Update

Major Activities over the Past Week

Over the past week the following project major activities performed at Phase 1 and 3 locations:

  • Between Ulysses and Arthur (Phase 1)

    • The first lift of asphalt pavement completed.
    • The storm sewer curb inlets raised into their final elevation.
    • Curb and gutter installed.
    • The driveway approach by the alleyways installed.
  • Between Arthur and Stinson (Phase 3)

    • The existing (old) storm sewer main line removal started.
    • The new storm sewer lateral connections and curb inlets installation started.

Coming Up

  • Phase 1:

    • The alleyways driveway approach installation will continue.
    • The post office east driveway approach will be installed
    • Concrete pavement on the stretch of Hayes St will be installed.
  • Phase 3:

    • Storm sewer and lateral connection and curb inlets will continue.
    • The old storm mainline removal will continue.
    • Weather permitting, grading work/ the road base preparation will begin

Traffic Impacts

  • The Post Office is still accessible through Johnson St. However, when we move into the Johnson intersection work, the access will be switched through Ulysses St and the driveway on the east.

  • The dead end alley between Arthur and Cleveland St: The alley access switched back through Arthur. However, depending on the amount of work in front of the alley entrance, the alley access might be switched to Cleveland again.

  • The business center by the Stinson is accessible through Stinson Blvd using the east driveway. The west driveway will remain closed till the new curb & gutter and asphalt pavement installed. Once we done these, we'll switch the access to the west entrance in order to finish up the remaining stretch up to Stinson intersection. This is just a heads up. We will notify/inform you the exact date a week before the traffic switch happen.

  • Other than the above considerations, 18th Ave between Ulysses and Stinson will remain closed except for local traffic.

Project Photos

18th Ave NE Construction Update 7-29-20_1

The 1st lift pavement - Phase1

18th Ave NE Construction Update 7-29-20_2

Curb and gutter installed - Phase 1

18th Ave NE Construction Update 7-29-20_3

Old storm sewer mainline removed - phase 3

18th Ave NE Construction Update 7-29-20_4

Storm sewer lateral connection - phase 3

July 19, 2020 Update

Major Activities over the Past Week

Over the past week the following project activities performed at Phase 1 and 3 locations:

  • Final grading and preparation work (Phase 1)

    • The final grading is completed between Ulysses and Arthur, and ready for the 1st lift asphalt pavement. It was planned to install the 1st lift of asphalt pavement last week. However, because of the mother nature the schedule postponed to early next week ( Monday 7/20).
    • The post office east side driveway removed. The new driveway will be installed after the 1st lift asphalt pavement placed.
  • Storm sewer installation (Phase 3)

    • Storm sewer mainline  installation between Stinson and Cleveland completed.
    • Between Cleveland and Arthur has started.
  • Water Main line (Phase 3)

    • An eight inch water line ( the service for the Quarry Target) lowered to avoid the conflict with the new storm sewer line.
    • Abandoned water lines removed between Cleveland and Stinson.
  • Electrical conduit and hand holes - ( Phase 1)

    • Egan Electric company installed the street light/ interconnect conduit and hand holes between Ulysses an Arthur

Coming Up

  • Phase 1: The 1st lift  asphalt pavement will be placed on Monday 7/20. (between Ulysses and Arthur).

  • Phase 3: Storm sewer system installation (main line and lateral connections) will continue between Cleveland and Arthur.

  • Weather permitting, curb and gutter installation work will start.

  • Phase 3: The existing (old) storm main line between Stinson and Arthur will be removed.

Traffic Impacts

  • The Post office is accessible through Johnson St.( weather permitting, the post office east side driveway will be installed by the end of next week.  Once the driveway cured, the post office access will be switched to this driveway through Ulysses ).

  • The dead end alley between Arthur and Cleveland St: The alley access switched from Arthur to Cleveland. Arthur intersection will be closed due to the storm sewer installation.

  • 18th Ave between Arthur and Stinson will remain closed except for local traffic.

  • The business center by the Stinson is accessible through Stinson Blvd using the east side driveway. The west driveway will remain closed.

Progress Photos

18th Ave NE construction photo 7-21-20_1

Installation of storm sewer main line and manhole near Cleveland St

18th Ave NE construction photo 7-21-20_2

The final grading/touch up between Ulysses and Arthur

18th Ave NE construction photo 7-21-20_3

Phase 1 is ready for the asphalt pavement

18th Ave NE construction photo 7-21-20_4

The 8" water service line that needed lowering to avoid conflict with the new storm line.

July 13, 2020 Update

Major Activities over the Past Week

Over the past week the following project activities performed at Phase 1 and 3 locations:

  • Soil correction and grading work ( Phase1)

    • Soil correction, grading and installation of class 5 material between Garfield St and Arthur St. completed.
    • The final grading is completed between Ulysses and Arthur. The stretch is ready for the 1st asphalt pavement lift.
    • The Sanitary upgrading work on Hayes St (about 75 LF) is completed and the section is ready for the concrete patching.
  • Storm sewer installation (Phase 3)

    • Storm sewer mainline  installation between Stinson and Benjamin on progress.
    • Storm inlets /Catch basins installation on progress

Coming Up

  • Phase 1: The 1st lift of asphalt pavement will be placed by the end of the week (Thursday and Friday).

  • Phase 3: Storm sewer system installation ( main line and lateral connections) will continue.

Note

  • On Monday, July 13, 2020, there will be night time construction work at  Benjamin St NE and 18th intersection to lower an 8-inch water service line that runs to the Quarry Target Store. To reduce the impact on the store, it's planned the work to be done between 10 pm and 6 am. All the communication and preparation work with the store management team has completed.

Traffic Impacts

  • The Post office is accessible through Johnson St. (when we move to phase 2, the post office will be accessible through Ulysses St. We will communicate for detail information soon).

  • 18th Ave between Arthur and Stinson will remain closed except for local traffic.

  • The business center by the Stinson is accessible through Stinson Blvd using the east side driveway. The west driveway will remain closed.

  • The dead end alley between Arthur and Cleveland St: when the  contractor installing the storm sewer mainline in front of the dead-end alley, there will be no access during the daytime between 7:00 AM and 5:00 PM. The garbage pick up services might be affected. However, we're working closely with the contractor the garbage trucks to get access on the collection day. We will communicate further if there is any changes.

Progress Photos

18th Ave NE Construction Photo 7-13-20_4

Placing class 5 material and grading work near Garfield intersection

18th Ave NE Construction Photo 7-13-20_1

Final grading between Ulysses and Arthur completed and ready for 1st lift asphalt pavement

18th Ave NE Construction Photo 7-13-20_2

 The sanitary upgrading work at the cross street (Hayes) completed and section is ready for concrete pavement.

18th Ave NE Construction Photo 7-13-20_3

Storm inlet/ catch basin installation at Benjamin intersection

July 6, 2020 Update

Major Activities over the Past Week

Over the past week the following project activities performed at Phase 1 and 3 locations

  • Soil correction and grading work - ( Phase1)

    • soil correction, grading and installation of class 5 material between Hayes and Garfield St performed.
  • Storm sewer installation - (Phase 3)

    • Storm sewer mainline installation continued which includes the main line pipe and manholes.

Coming Up

  • Storm sewer system installation will continue. (Phase 3)

  • Soil correction, subgrade preparation and placing class v material will continue between Garfield and Arthur St. (phase 1) Traffic Impacts : The impact will remain as it was last week.

The Post office is accessible through Johnson St. (when we move to phase 2, the post office will be accessible through Ulysses St . We will communicate for detail information soon).

  • 18th Ave between Arthur and Stinson will remain closed except for local traffic.

  • The east side driveway located by the business center near Stinson Blvd will remain open and accessible. The west driveway will remain closed.

The dead end alley between Arthur and Cleveland St. will keep open and accessible through Arthur St. for the garbage pick up services too.

Progress Photos

18th Ave NE Construction Photo 7-6-20_1

Underground utility work completed between Ulysses and Garfield

18th Ave NE Construction Photo 7-6-20_2

 Storm sewer mainline installation

18th Ave NE Construction Photo 7-6-20_3

12 ft diameter storm sewer manhole

June 29, 2020 Update

Major Activities over the Past Week

Over the past week the following project activities performed at Phase 1 and 3 locations

  • Storm sewer installation on phase 1

    • The Installation of the largest storm manhole structure (10 LF in diameter and 14 LF deep) near to the business area west driveway by the Stinson intersection completed. (phase 3)
    • The storm sewer lateral connections / catch basins installation up to Garfield St performed (phase 1)
  • Soil correction, subgrade preparation and placing class v material between Ulysses and Hayes St  performed.(phase1)

Coming Up

  • Storm sewer system installation will continue  (phase1&3)

  • Soil correction, subgrade preparation and placing class v material between Hayes St  and Garfield St (phase 1)

  • Water work (relocating gate valves) near Arthur intersection (phase 1)

Traffic Impacts

  • 18th Ave between Arthur and Stinson will remain closed except for local traffic.

  • The east side driveway located by the business center near Stinson Blvd will remain open and accessible. The west driveway will remain closed .

  • The dead end alley between Arthur and Cleveland St. will keep open and accessible through Arthur St. The access getting wider to accommodate the garbage pick up services.

  • The Post office is accessible through Johnson St. (when we move to phase 2, the post office will be accessible through Ulysses St . We will communicate for detail information soon).

Progress Photos

18th Ave NE Construction Photo 6-29-20_1

Progress on 18th Ave NE.

18th Ave NE Construction Photo 6-29-20_2

Soil correction, backfill and Class V material placement (phase 1)

18th Ave NE Construction Photo 6-29-20_3

The 10LF diameter storm sewer manhole installation

June 22, 2020 Update

Major Activities over the Past Week

Over the past week the project activities focused on Phase 1 and 3

  • Storm sewer installation on phase 1

    • main line and lateral installation between Ulysses and Garfield ~ 840 LF completed
  • Pavement removal on phase 3 completed except around Stinson intersection area. This will give a relief for business access near the Stinson intersection.

Coming Up

  • The main Storm manhole structure (10 LF in diameter and 14 LF deep) will be installed near to the business area west driveway by the Stinson intersection. ( Phase 3)

  • Storm sewer system installation will continue between Garfield and Arthur (Phase1)

  • Backfill and grading will start from Ulysses towards east. (Phase 1)

Traffic Impacts

  • The Post office is accessible through Johnson St. ( the access might change when we move to phase 2. Detail information will come soon).

  • 18th Ave between Arthur and Stinson will remain closed except for local traffic.

  • The east side driveway located by the business center near Stinson Blvd will remain open and accessible. The west driveway will be closed during.

  • The dead end alley between Arthur and Cleveland St.; We will keep the alley open and accessible through Arthur St.

  • For those who have access through the side streets, we encourage you to use 19th Ave NE.

Progress Photos

18th Ave NE Construction Photo 6-23-20_1

Pavement removal completed up to the west driveway near Stinson Blvd

18th Ave NE Construction Photo 6-23-20_2

Installation of storm sewer system (Phase 1)

18th Ave NE Construction Photo 6-23-20_3

Access to the dead-end alley (between Arthur and Cleveland)

June 10, 2020 Interim Update

We would like to inform you that the project contractor is ahead of the schedule and will start pavement removal work on Phase 3 (Arthur St NE to Stinson Blvd NE) starting on Thursday, June 11, 2020. The schedule is different from what was stated in the previous update, but it will bring a good opportunity to speed up the project activities.

What will it impact?

  • 18th Ave NE between Arthur and Stinson will be closed except for local traffic.

  • The two driveways located by the business center near Stinson Blvd will remain open for this week and weekend. Then starting next week the west driveway will be closed, but the east driveway will remain open and accessible.

  • We know there is a dead end alley between Arthur and Cleveland St.; We will keep the alley open and accessible through Arthur St.

  • For those who have access through the side streets, we encourage you to use 19th Ave NE.

June 8, 2020 Update

Planned Construction Activity Phases

  • Phase 1: Ulysses to Arthur

  • Phase 2: Johnson to Ulysses

  • Phase 3: Arthur to Stinson

  • Phase 4: Stinson intersection

Update on the Activity Phases

As mentioned in the previous weekly update, we will have the construction phases sequential order change. Once the activities in Phase completed, we will move to Phase 3 instead of Phase 2.

Major Activities over the Past Week (Phase 1: Ulysses to Arthur)

Over the past week the project activities focused on Phase 1:

  • Sanitary sewer bypass installed.

  • Sanitary sewer main line replacement completed between Ulysses and Garfield

  • Air test conducted in the newly installed sewer system.

Coming Up

  • Storm sewer system installation will start (Phase 1).

  • Sanitary mainline replacement on Hayes St NE segment (Phase 1).

Traffic Impacts

  • The Post office is accessible through Johnson St.

  • Ulysses St to Arthur under construction and completely closed for traffic except for garbage collector trucks and for those residents whom they have access only through 18th.

  • Arthur St to Stinson also closed for through traffic, however; since pavement removal not started in this segment, 18th is accessible for local traffic.

Progress Photos

18th Ave NE Construction Photo 6-8-20_3

18th Ave NE Construction  Photo 6-8-20_2

May 26, 2020 Update

The 18th Ave NE (Johnson to Stinson) road reconstruction project started on May 18, 2020.

The project will follow the following construction stages order. However, with different conditions and unknown circumstances the orders might change.

Construction Stages

  1. Ulysses  to Arthur

  2. Johnson  to Ulysses

  3. Arthur to Stinson

  4. Stinson intersection

Major Activities in the Past Week (Stage 1: Ulysses to Arthur)

  • The Contractor mobilized to the project site.

  • The required Traffic control signs set up.

  • Pavement removal has started between Ulysses and Arthur St NE

  • Sanitary mainline replacement has started at Ulysses intersection

Traffic Impacts

In the first stage work, 18th Ave NE from Johnson to Arthur completely closed, except Post office access at Johnson. This scenario will continue till the 1st stage completed.  The remaining portion of the road from Arthur to Stinson is also closed for through traffic, however; since pavement removal not started in this segment, 18th is accessible for local traffic.

Coming Up

  • The commenced activities on the 1st stage will continue.

  •  Utility upgrade (Storm and Sanitary mainline replacement) will continue.

Progress Photos

18th Ave NE Construction Photo 5-26-20_1

The left turn from Johnson St to 18th Ave NE is closed except access to the post office only.

18th Ave NE Construction Photo 5-26-20_3

Removal of pavement

18th Ave NE Construction Photo 5-26-20_4

Gaining access to sewer mainline

April 29, 2020 Update

Utility Construction on 18th Ave NE began on Monday, March 30, 2020 and will run through late May 2020.

Major Activity in the Past Two Weeks

  • There was no much activity form Centerpoint

  • Most the restoration work completed except near the intersection with NE Garfield St

  • City Traffic working on the temporary signal system at 18th and Johnson intersection.

Work Expected in the Next Week

  • Restoration work will continue on the remaining portion of 18th Ave NE

Traffic impacts: The east bound lane closed for the restoration work at Garfield St NE. It will be opened once restoration completed. The CenterPoint will notify residents or business owners if the crews need to cross any driveways.

18th Ave NE street reconstruction work is expected to start in mid-to late May as CenterPoint finishes their project.

Progress

Mid City Industrial Phase 2 Photo 4-29-20_1

Temporary signal work installation at 18th and Johnson intersection

Mid City Industrial Phase 2 Photo 4-29-20_2

The remaining restoration work to be done (above and below)

Mid City Industrial Phase 2 Photo 4-29-20_3

April 22, 2020 Update

Utility Construction on 18th Ave NE began Monday, March 30 and will run through late May 2020.

18th Ave NE street reconstruction work is expected to start in mid-to late May as CenterPoint finishes their project.

Major Activities in the Past Two Weeks

  • Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, has completed all gas main installation and in service.

  • The major two service lines installation completed

  • Restoration work has completed at Stinson and 18th Ave NE Intersection, and the lane is widely open

What to Expect in the Next Week

  • CenterPoint will continue the remaining service work and abandonment of the old system in the next couple weeks.

  • Restoration work will continue on the remaining portion of 18th Ave NE

Traffic Impact

The east bound lane closed for the restoration work. It will be opened once restoration completed. The CenterPoint will notify residents or business owners if the crews need to cross any driveways.

Progress

18th Ave NE Construction Photo 4-24-20_1

Directional boring

18th Ave NE Construction Photo 4-24-20_2

Gas main installation

Sign up for email updates

 

Email Updates

 

To sign up for email updates, please enter your contact information below.

Contact us

Ayalew Getaneh, Construction Engineer; 612-673-6055 or Ayale[email protected]

Beverly Warmka, Design Engineer; 612-673-3762 or [email protected]

 

Last updated Oct 21, 2020

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-263-6850.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

Public Works  ©1997-2020 City of Minneapolis, MN

CONNECT

311 call center

311 TTY relay service

City of Minneapolis Facebook City of Minneapolis Twitter City of Minneapolis YouTube ChaNNEL Minneapolis 311 Watch Minneapolis City Council TV City of Minneapolis LinkedIn

Minneapolis, City of Lakes logo