18th Ave NE Reconstruction

(Johnson St NE to Stinson Blvd)

In 2020, the City of Minneapolis will be reconstructing 18th Ave NE in northeast Minneapolis between Johnson St NE and Stinson Blvd.

18th Ave NE Johnson to Stinson Webmap 11-5-18

Project status

Project Status: Construction

Project details

Description

The City of Minneapolis is planning to reconstruct approximately 0.5 miles of 18th Avenue NE in the Northeast Park and Windom Park neighborhoods. The project will replace aging pavement and improve the right-of-way for all users and modes of travel. This project provides an opportunity to incorporate ADA compliant pedestrian ramps, address sidewalk obstructions and sidewalk/trail gaps, and add boulevard space with street trees. The project will connect into the recently constructed trail to west along 18th Ave NE.

See the recommended design for the 18th Ave NE project.

Project Type

The project includes full reconstruction of the entire right-of-way and will include filling sidewalk gaps, ADA pedestrian ramps, boulevard space, pavement, curb and gutter, and utility improvements. The project will also include new signage, new pavement markings, and improve non-motorized crossings to Northeast Minneapolis’ major retail center.

Project Limits

Approximately 0.5 miles of 18th Avenue NE between Johnson Street NE and Stinson Parkway.

Project Timeline

18th Ave NE Street Reconstruction Timeline Graphic

Utility Construction on 18th Ave NE will begin Monday, March 30 and run through late May 2020.

CenterPoint Energy’s project is anticipated to last two months. Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, will replace natural gas mains and connect natural gas service lines to the new mains.

18th Ave NE street reconstruction work is expected to start in mid-to late May as CenterPoint finishes their utility work.

Traffic Impacts

On 18th Avenue NE, crews from Michels Corporation will begin at Stinson Parkway working west. Each block will be closed for approximately one to two weeks. Eastbound traffic will be detoured. CenterPoint will notify residents or business owners if the crews need to cross any driveways.

During construction, residents, businesses, and visitors may expect traffic detours, noise, vibration, and dust in work areas. In addition, temporary impacts such as lane restrictions, intersection reductions, parking restrictions or revised pedestrian and bicycle routes may be expected during construction. Property access will be maintained throughout construction. Specific construction staging and traffic detour information will be posted here as the project gets closer to construction.

Project Meetings

Weekly Stakeholder Meeting Reminder

Virtual weekly project stakeholder meetings will be held every Thursday using Microsoft Teams. Please use the link below to join the meeting.

Join the Virtual Weekly Stakeholders Meeting

Every Thursday, 11:00 - 11:30 a.m.

These meetings help us to give you more detailed information about work progress on a weekly basis and to have discussion on any concerns or questions you have about the project. Please send me (Ayalew) an email or give me a call if you have difficulty using the link above.

If no one joins the meeting within 15 minutes the meeting will end, but you can still contact me via phone or email.

Ayalew Getaneh, Construction Engineer; 612-673-6055 or [email protected]

Documents

Project Fact Sheet

Recommended Layout - May 2019

18th Ave NE Virtual Construction Kick-off Meeting Presentation - May 13, 2020

Project updates

August 10, 2020 Update

Major Activities over the Past Week

Over the past week the following project major activities were completed at Phase 1 and 3 locations:

  • Between Ulysses and Arthur (Phase1)
    • Bus pads installed.
    • Sidewalk and pedestrian crossing ramps installation continued.
  • Between Arthur and Stinson (Phase 3)
    • The road base (subgrade) preparation and soil correction work performed.
    • Placing class v material started.
    • Plug and fill of abandoned in place storm sewer line conducted .

Coming Up

  • Phase 1:
    • The next 2 lifts of asphalt pavement will be placed, weather permitting.
    • Restoration work behind the curb will continue.
  • Phase 3:
    • The road base (subgrade) preparation and soil correction work will continue.
    • The final grading will be done and the phase will be ready for the 1st lift of asphalt pavement, weather permitting.
    • The lighting and traffic signal connection conduit and handholds will be installed.

Traffic Impacts

Traffic impacts will remain the same as the last week.

  • The work on Johnson intersection will start on the week of August 18th. Till then the Post Office is still accessible through Johnson St. However, when we move into the Johnson intersection work, the access will be switched through Hayes St and the driveway on the east. We planned Ulysses to be a detour for the post office access. However, there are some remaining work at the at this intersection and decided to use Hayes as the access detour.
  • The dead end alley between Arthur and Cleveland St: The alley access switched back through Arthur. However, depending on the amount of work in front of the alley entrance, the alley access might be switched to Cleveland again.
  • The business center by the Stinson is accessible through Stinson Blvd using the east driveway. The west driveway will remain closed till the new curb & gutter and asphalt pavement installed. Once we done these, we'll switch the access to the west entrance in order to finish up the remaining stretch up to Stinson intersection. This is just a heads up. We will notify/inform you the exact date a week before the traffic switch happen.
  • Other than the above considerations, 18th Ave between Ulysses and Stinson will remain closed except for local traffic.

Progress Photos

18th Ave NE Construction Photos 8-10-20_1

Bus pad installed at Hayes intersection - Phase 1

18th Ave NE Construction Photos 8-10-20_2

Soil correction - Phase 3

18th Ave NE Construction Photos 8-10-20_3

Placing class v material after the soil correction is done

18th Ave NE Construction Photos 8-10-20_4

July 31, 2020 Update

Major Activities over the Past Week

Over the past week the following project major activities performed at Phase 1 and 3 locations:

  • Between Ulysses and Arthur (Phase 1)
    • The alleyways driveway approaches installed and completed.
    • The post office east driveway approach installed. When the concrete cured, the gap behind the driveway will be patched with asphalt.
    • Concrete pavement restoration on Hayes St stretch completed.
    • Sidewalk and pedestrian crossing ramps installation started.
  • Between Arthur and Stinson (Phase 3)
    • The existing (old) storm sewer main line removal completed.
    • The new storm sewer lateral connections and curb inlets installation completed.
    • Sanitary manhole re-construct completed.

Coming Up

  • Phase 1
    • Sidewalk and pedestrian crossing ramps installation will continue.
    • Bus pad will install.
    • Restoration work behind the curb.
  • Phase 3
    • The road base (subgrade) preparation and soil correction work.

Traffic Impacts

  • The traffic impacts will remain the same as the last week.

    • The Post Office is still accessible through Johnson St. However, when we move into the Johnson intersection work, the access will be switched through Ulysses St and the driveway on the east.
    • The dead end alley between Arthur and Cleveland St: The alley access switched back through Arthur. However, depending on the amount of work in front of the alley entrance, the alley access might be switched to Cleveland again.
    • The business center by the Stinson is accessible through Stinson Blvd using the east driveway. The west driveway will remain closed till the new curb & gutter and asphalt pavement installed. Once we done these, we'll switch the access to the west entrance in order to finish up the remaining stretch up to Stinson intersection. This is just a heads up. We will notify/inform you the exact date a week before the traffic switch happen.
    • Other than the above considerations, 18th Ave between Ulysses and Stinson will remain closed except for local traffic.

Progress Photos

18th Ave NE Construction Photo 7-31-20_1

The Post Office east driveway installed (Phase 1)

18th Ave NE Construction Photo 7-31-20_2

Concrete pavement restoration on Hayes St after the sanitary mainline replacement (Phase 1)

18th Ave NE Construction Photo 7-31-20_3

Sidewalk and pedestrian crossing ramp (Phase 1)

18th Ave NE Construction Photo 7-31-20_4

Sanitary manhole section removal (Phase 3)

18th Ave NE Construction Photo 7-31-20_5

Sanitary manhole reconstruction (Phase 3)

July 24, 2020 Update

Major Activities over the Past Week

Over the past week the following project major activities performed at Phase 1 and 3 locations:

  • Between Ulysses and Arthur (Phase 1)
    • The first lift of asphalt pavement completed.
    • The storm sewer curb inlets raised into their final elevation.
    • Curb and gutter installed.
    • The driveway approach by the alleyways installed.
  • Between Arthur and Stinson (Phase 3)
    • The existing (old) storm sewer main line removal started.
    • The new storm sewer lateral connections and curb inlets installation started.

Coming Up

  • Phase 1:
    • The alleyways driveway approach installation will continue.
    • The post office east driveway approach will be installed
    • Concrete pavement on the stretch of Hayes St will be installed.
  • Phase 3:
    • Storm sewer and lateral connection and curb inlets will continue.
    • The old storm mainline removal will continue.
    • Weather permitting, grading work/ the road base preparation will begin

Traffic Impacts

  • The Post Office is still accessible through Johnson St. However, when we move into the Johnson intersection work, the access will be switched through Ulysses St and the driveway on the east.
  • The dead end alley between Arthur and Cleveland St: The alley access switched back through Arthur. However, depending on the amount of work in front of the alley entrance, the alley access might be switched to Cleveland again.
  • The business center by the Stinson is accessible through Stinson Blvd using the east driveway. The west driveway will remain closed till the new curb & gutter and asphalt pavement installed. Once we done these, we'll switch the access to the west entrance in order to finish up the remaining stretch up to Stinson intersection. This is just a heads up. We will notify/inform you the exact date a week before the traffic switch happen.
  • Other than the above considerations, 18th Ave between Ulysses and Stinson will remain closed except for local traffic.

Project Photos

18th Ave NE Construction Update 7-29-20_1

The 1st lift pavement - Phase1

18th Ave NE Construction Update 7-29-20_2

Curb and gutter installed - Phase 1

18th Ave NE Construction Update 7-29-20_3

Old storm sewer mainline removed - phase 3

18th Ave NE Construction Update 7-29-20_4

Storm sewer lateral connection - phase 3

July 19, 2020 Update

Major Activities over the Past Week

Over the past week the following project activities performed at Phase 1 and 3 locations:

  • Final grading and preparation work (Phase 1)
    • The final grading is completed between Ulysses and Arthur, and ready for the 1st lift asphalt pavement. It was planned to install the 1st lift of asphalt pavement last week. However, because of the mother nature the schedule postponed to early next week ( Monday 7/20).
    • The post office east side driveway removed. The new driveway will be installed after the 1st lift asphalt pavement placed.
  • Storm sewer installation (Phase 3)
    • Storm sewer mainline  installation between Stinson and Cleveland completed.
    • Between Cleveland and Arthur has started.
  • Water Main line (Phase 3)
    • An eight inch water line ( the service for the Quarry Target) lowered to avoid the conflict with the new storm sewer line.
    • Abandoned water lines removed between Cleveland and Stinson.
  • Electrical conduit and hand holes - ( Phase 1)
    • Egan Electric company installed the street light/ interconnect conduit and hand holes between Ulysses an Arthur

Coming Up

  • Phase 1: The 1st lift  asphalt pavement will be placed on Monday 7/20. (between Ulysses and Arthur).
  • Phase 3: Storm sewer system installation (main line and lateral connections) will continue between Cleveland and Arthur.
  • Weather permitting, curb and gutter installation work will start.
  • Phase 3: The existing (old) storm main line between Stinson and Arthur will be removed.

Traffic Impacts

  • The Post office is accessible through Johnson St.( weather permitting, the post office east side driveway will be installed by the end of next week.  Once the driveway cured, the post office access will be switched to this driveway through Ulysses ).
  • The dead end alley between Arthur and Cleveland St: The alley access switched from Arthur to Cleveland. Arthur intersection will be closed due to the storm sewer installation.
  • 18th Ave between Arthur and Stinson will remain closed except for local traffic.
  • The business center by the Stinson is accessible through Stinson Blvd using the east side driveway. The west driveway will remain closed.

Progress Photos

18th Ave NE construction photo 7-21-20_1

Installation of storm sewer main line and manhole near Cleveland St

18th Ave NE construction photo 7-21-20_2

The final grading/touch up between Ulysses and Arthur

18th Ave NE construction photo 7-21-20_3

Phase 1 is ready for the asphalt pavement

18th Ave NE construction photo 7-21-20_4

The 8" water service line that needed lowering to avoid conflict with the new storm line.

July 13, 2020 Update

Major Activities over the Past Week

Over the past week the following project activities performed at Phase 1 and 3 locations:

  • Soil correction and grading work ( Phase1)
    • Soil correction, grading and installation of class 5 material between Garfield St and Arthur St. completed.
    • The final grading is completed between Ulysses and Arthur. The stretch is ready for the 1st asphalt pavement lift.
    • The Sanitary upgrading work on Hayes St (about 75 LF) is completed and the section is ready for the concrete patching.
  • Storm sewer installation (Phase 3)
    • Storm sewer mainline  installation between Stinson and Benjamin on progress.
    • Storm inlets /Catch basins installation on progress

Coming Up

  • Phase 1: The 1st lift of asphalt pavement will be placed by the end of the week (Thursday and Friday).
  • Phase 3: Storm sewer system installation ( main line and lateral connections) will continue.

Note

  • On Monday, July 13, 2020, there will be night time construction work at  Benjamin St NE and 18th intersection to lower an 8-inch water service line that runs to the Quarry Target Store. To reduce the impact on the store, it's planned the work to be done between 10 pm and 6 am. All the communication and preparation work with the store management team has completed.

Traffic Impacts

  • The Post office is accessible through Johnson St. (when we move to phase 2, the post office will be accessible through Ulysses St. We will communicate for detail information soon).
  • 18th Ave between Arthur and Stinson will remain closed except for local traffic.
  • The business center by the Stinson is accessible through Stinson Blvd using the east side driveway. The west driveway will remain closed.
  • The dead end alley between Arthur and Cleveland St: when the  contractor installing the storm sewer mainline in front of the dead-end alley, there will be no access during the daytime between 7:00 AM and 5:00 PM. The garbage pick up services might be affected. However, we're working closely with the contractor the garbage trucks to get access on the collection day. We will communicate further if there is any changes.

Progress Photos

18th Ave NE Construction Photo 7-13-20_4

Placing class 5 material and grading work near Garfield intersection

18th Ave NE Construction Photo 7-13-20_1

Final grading between Ulysses and Arthur completed and ready for 1st lift asphalt pavement

18th Ave NE Construction Photo 7-13-20_2

 The sanitary upgrading work at the cross street (Hayes) completed and section is ready for concrete pavement.

18th Ave NE Construction Photo 7-13-20_3

Storm inlet/ catch basin installation at Benjamin intersection

July 6, 2020 Update

Major Activities over the Past Week

Over the past week the following project activities performed at Phase 1 and 3 locations

  • Soil correction and grading work - ( Phase1)
    • soil correction, grading and installation of class 5 material between Hayes and Garfield St performed.
  • Storm sewer installation - (Phase 3)
    • Storm sewer mainline installation continued which includes the main line pipe and manholes.

Coming Up

  • Storm sewer system installation will continue. (Phase 3)
  • Soil correction, subgrade preparation and placing class v material will continue between Garfield and Arthur St. (phase 1) Traffic Impacts : The impact will remain as it was last week.

The Post office is accessible through Johnson St. (when we move to phase 2, the post office will be accessible through Ulysses St . We will communicate for detail information soon).

  • 18th Ave between Arthur and Stinson will remain closed except for local traffic.
  • The east side driveway located by the business center near Stinson Blvd will remain open and accessible. The west driveway will remain closed.

The dead end alley between Arthur and Cleveland St. will keep open and accessible through Arthur St. for the garbage pick up services too.

Progress Photos

18th Ave NE Construction Photo 7-6-20_1

Underground utility work completed between Ulysses and Garfield

18th Ave NE Construction Photo 7-6-20_2

 Storm sewer mainline installation

18th Ave NE Construction Photo 7-6-20_3

12 ft diameter storm sewer manhole

June 29, 2020 Update

Major Activities over the Past Week

Over the past week the following project activities performed at Phase 1 and 3 locations

  • Storm sewer installation on phase 1
    • The Installation of the largest storm manhole structure (10 LF in diameter and 14 LF deep) near to the business area west driveway by the Stinson intersection completed. (phase 3)
    • The storm sewer lateral connections / catch basins installation up to Garfield St performed (phase 1)
  • Soil correction, subgrade preparation and placing class v material between Ulysses and Hayes St  performed.(phase1)

Coming Up

  • Storm sewer system installation will continue  (phase1&3)
  • Soil correction, subgrade preparation and placing class v material between Hayes St  and Garfield St (phase 1)
  • Water work (relocating gate valves) near Arthur intersection (phase 1)

Traffic Impacts

  • 18th Ave between Arthur and Stinson will remain closed except for local traffic.
  • The east side driveway located by the business center near Stinson Blvd will remain open and accessible. The west driveway will remain closed .
  • The dead end alley between Arthur and Cleveland St. will keep open and accessible through Arthur St. The access getting wider to accommodate the garbage pick up services.
  • The Post office is accessible through Johnson St. (when we move to phase 2, the post office will be accessible through Ulysses St . We will communicate for detail information soon).

Progress Photos

18th Ave NE Construction Photo 6-29-20_1

Progress on 18th Ave NE.

18th Ave NE Construction Photo 6-29-20_2

Soil correction, backfill and Class V material placement (phase 1)

18th Ave NE Construction Photo 6-29-20_3

The 10LF diameter storm sewer manhole installation

June 22, 2020 Update

Major Activities over the Past Week

Over the past week the project activities focused on Phase 1 and 3

  • Storm sewer installation on phase 1
    • main line and lateral installation between Ulysses and Garfield ~ 840 LF completed
  • Pavement removal on phase 3 completed except around Stinson intersection area. This will give a relief for business access near the Stinson intersection.

Coming Up

  • The main Storm manhole structure (10 LF in diameter and 14 LF deep) will be installed near to the business area west driveway by the Stinson intersection. ( Phase 3)
  • Storm sewer system installation will continue between Garfield and Arthur (Phase1)
  • Backfill and grading will start from Ulysses towards east. (Phase 1)

Traffic Impacts

  • The Post office is accessible through Johnson St. ( the access might change when we move to phase 2. Detail information will come soon).
  • 18th Ave between Arthur and Stinson will remain closed except for local traffic.
  • The east side driveway located by the business center near Stinson Blvd will remain open and accessible. The west driveway will be closed during.
  • The dead end alley between Arthur and Cleveland St.; We will keep the alley open and accessible through Arthur St.
  • For those who have access through the side streets, we encourage you to use 19th Ave NE.

Progress Photos

18th Ave NE Construction Photo 6-23-20_1

Pavement removal completed up to the west driveway near Stinson Blvd

18th Ave NE Construction Photo 6-23-20_2

Installation of storm sewer system (Phase 1)

18th Ave NE Construction Photo 6-23-20_3

Access to the dead-end alley (between Arthur and Cleveland)

June 10, 2020 Interim Update

We would like to inform you that the project contractor is ahead of the schedule and will start pavement removal work on Phase 3 (Arthur St NE to Stinson Blvd NE) starting on Thursday, June 11, 2020. The schedule is different from what was stated in the previous update, but it will bring a good opportunity to speed up the project activities.

What will it impact?

  • 18th Ave NE between Arthur and Stinson will be closed except for local traffic.
  • The two driveways located by the business center near Stinson Blvd will remain open for this week and weekend. Then starting next week the west driveway will be closed, but the east driveway will remain open and accessible.
  • We know there is a dead end alley between Arthur and Cleveland St.; We will keep the alley open and accessible through Arthur St.
  • For those who have access through the side streets, we encourage you to use 19th Ave NE.

June 8, 2020 Update

Planned Construction Activity Phases

  • Phase 1: Ulysses to Arthur
  • Phase 2: Johnson to Ulysses
  • Phase 3: Arthur to Stinson
  • Phase 4: Stinson intersection

Update on the Activity Phases

As mentioned in the previous weekly update, we will have the construction phases sequential order change. Once the activities in Phase completed, we will move to Phase 3 instead of Phase 2.

Major Activities over the Past Week (Phase 1: Ulysses to Arthur)

Over the past week the project activities focused on Phase 1:

  • Sanitary sewer bypass installed.
  • Sanitary sewer main line replacement completed between Ulysses and Garfield
  • Air test conducted in the newly installed sewer system.

Coming Up

  • Storm sewer system installation will start (Phase 1).
  • Sanitary mainline replacement on Hayes St NE segment (Phase 1).

Traffic Impacts

  • The Post office is accessible through Johnson St.
  • Ulysses St to Arthur under construction and completely closed for traffic except for garbage collector trucks and for those residents whom they have access only through 18th.
  • Arthur St to Stinson also closed for through traffic, however; since pavement removal not started in this segment, 18th is accessible for local traffic.

Progress Photos

18th Ave NE Construction Photo 6-8-20_3

18th Ave NE Construction  Photo 6-8-20_2

May 26, 2020 Update

The 18th Ave NE (Johnson to Stinson) road reconstruction project started on May 18, 2020.

The project will follow the following construction stages order. However, with different conditions and unknown circumstances the orders might change.

Construction Stages

  1. Ulysses  to Arthur
  2. Johnson  to Ulysses
  3. Arthur to Stinson
  4. Stinson intersection

Major Activities in the Past Week (Stage 1: Ulysses to Arthur)

  • The Contractor mobilized to the project site.
  • The required Traffic control signs set up.
  • Pavement removal has started between Ulysses and Arthur St NE
  • Sanitary mainline replacement has started at Ulysses intersection

Traffic Impacts

In the first stage work, 18th Ave NE from Johnson to Arthur completely closed, except Post office access at Johnson. This scenario will continue till the 1st stage completed.  The remaining portion of the road from Arthur to Stinson is also closed for through traffic, however; since pavement removal not started in this segment, 18th is accessible for local traffic.

Coming Up

  • The commenced activities on the 1st stage will continue.
  •  Utility upgrade (Storm and Sanitary mainline replacement) will continue.

Progress Photos

18th Ave NE Construction Photo 5-26-20_1

The left turn from Johnson St to 18th Ave NE is closed except access to the post office only.

18th Ave NE Construction Photo 5-26-20_3

Removal of pavement

18th Ave NE Construction Photo 5-26-20_4

Gaining access to sewer mainline

April 29, 2020 Update

Utility Construction on 18th Ave NE began on Monday, March 30, 2020 and will run through late May 2020.

Major Activity in the Past Two Weeks

  • There was no much activity form Centerpoint
  • Most the restoration work completed except near the intersection with NE Garfield St
  • City Traffic working on the temporary signal system at 18th and Johnson intersection.

Work Expected in the Next Week

  • Restoration work will continue on the remaining portion of 18th Ave NE

Traffic impacts: The east bound lane closed for the restoration work at Garfield St NE. It will be opened once restoration completed. The CenterPoint will notify residents or business owners if the crews need to cross any driveways.

18th Ave NE street reconstruction work is expected to start in mid-to late May as CenterPoint finishes their project.

Progress

Mid City Industrial Phase 2 Photo 4-29-20_1

Temporary signal work installation at 18th and Johnson intersection

Mid City Industrial Phase 2 Photo 4-29-20_2

The remaining restoration work to be done (above and below)

Mid City Industrial Phase 2 Photo 4-29-20_3

April 22, 2020 Update

Utility Construction on 18th Ave NE began Monday, March 30 and will run through late May 2020.

18th Ave NE street reconstruction work is expected to start in mid-to late May as CenterPoint finishes their project.

Major Activities in the Past Two Weeks

  • Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, has completed all gas main installation and in service.
  • The major two service lines installation completed
  • Restoration work has completed at Stinson and 18th Ave NE Intersection, and the lane is widely open

What to Expect in the Next Week

  • CenterPoint will continue the remaining service work and abandonment of the old system in the next couple weeks.
  • Restoration work will continue on the remaining portion of 18th Ave NE

Traffic Impact

The east bound lane closed for the restoration work. It will be opened once restoration completed. The CenterPoint will notify residents or business owners if the crews need to cross any driveways.

Progress

18th Ave NE Construction Photo 4-24-20_1

Directional boring

18th Ave NE Construction Photo 4-24-20_2

Gas main installation

Sign up for email updates

Email Updates
To sign up for email updates, please enter your contact information below.

Contact us

Ayalew Getaneh, Construction Engineer; 612-673-6055 or [email protected]

Beverly Warmka, Design Engineer; 612-673-3762 or [email protected]

 

Last updated Aug 10, 2020

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-263-6850.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

Public Works  ©1997-2020 City of Minneapolis, MN

CONNECT

311 call center

311 TTY relay service

City of Minneapolis Facebook City of Minneapolis Twitter City of Minneapolis YouTube ChaNNEL Minneapolis 311 Watch Minneapolis City Council TV City of Minneapolis LinkedIn

Minneapolis, City of Lakes logo